Sole source, single source and emergency procurements are examples of:
A. The best ways of procuring goods and services.
B. Non-competitive methods of procuring goods and services.
C. Unauthorized procurement methods.
D. Procurement methods of questionable value.
B. Non-competitive methods of procuring goods and services.
In preparing to write a specification or scope of work, we may want to consider one of two
methods of gathering facts or details from potential vendors. We can invite several of them to
come to our agency and make a presentation or we can cast a wider net with this technique
A. Request for qualifications
B. Request for proposals
C. Request for information
D. Request for exemption
C. Request for information
This seller pricing strategy, in which prices are defined by the range of products offered, is
known as:
A. Market-oriented
B. Cost-based
C. Market-based
, CPPO Prep Exam | Accurate Questions and
accurate Answers| Latest 2026/ 2027 Update
|Grade A (Complete Solutions)
D. Value-based
A. Market-oriented
The common law rule that prevents extrinsic evidence of past agreements or terms from being
considered when interpreting an existing contract is known as the
A. Parole Evidence Rule
B. Parol Evidence Rule
C. Petrol Evidence Rule
D. Payroll Evidence Rule
B. Parol Evidence Rule
This item in a strategic plan describes the agency's purpose for existing.
Mission Statement.
Why is the Request for Proposal (RFP) process often perceived as problematic by an agency's
leadership?
A. The award decision is very quantifiable.
B. The award decision is based on qualitative variables.
C. The price is rarely known on award.
D. The outcome of the RFP process is difficult to justify.
B. The award decision is based on qualitative variables.
, CPPO Prep Exam | Accurate Questions and
accurate Answers| Latest 2026/ 2027 Update
|Grade A (Complete Solutions)
A university is prepared to sign a contract to add 10 classrooms for a new program. Registration
for the program will begin in 9 months if the project is completed on time and 6 months if the
contractor completes the project early. During the negotiations, the university offered the
contractor an additional $50,000 to complete the project in six months. What type of contract
pricing is the university using?
A. Fixed-price with redetermination
B. Fixed-price incentive
C. Cost sharing
D. Cost plus fixed fee
B. Fixed-price incentive
Laws governing public records, open meetings and freedom of information are known by this
illuminating phrase.
The Sunshine Law
Which of the following analysis methods looks at the availability of competition and alternative
products?
A. Demand analysis
B. Market analysis
C. Supplier analysis
D. Value analysis
C. Supplier analysis
The ABA Model Procurement Code lists six methods of source selection
, CPPO Prep Exam | Accurate Questions and
accurate Answers| Latest 2026/ 2027 Update
|Grade A (Complete Solutions)
Competitive Sealed Bids
Competitive Sealed Proposals
Small Purchases
Sole Source Procurement
Emergency Procurement
Competitive Selection for Services or Architect-Engineer and Land Surveying Services.
Unity of command; equality of authority & responsibility; and span of control & delegation are
three essential principles of which aspect of management?
A. Staffing
B. Planning
C. Directing
D. Organizing
D. Organizing
Strategies identify methods to achieve specific goals. Goals identify what the organization wants
to achieve and objectives identify...
A. When the goals will be carried out.
B. Where the goals will take place.
C. How the goals are to be carried out.
D. How the goals will improve the budget.
C. How the goals are to be carried out.