PK0-004 Project+ BEST STUDY GUIDE 2021/2022
PK0-004 Project+ BEST STUDY GUIDE 2021/2022A milestone task on the critical path has been completed. 
 
which of the following should the project manager notify? 
 
A owner of predecessor task 
B project team 
C project sponsor 
D project steering committee correct answer- C 
 
During a project assessment, a project manager determines the initial project cost estimates were incorrect oh, and there is not enough budget left, including reserves, to complete the project. 
 
Which of the followi...
- Exam (elaborations)
- • 159 pages's •
-
PK0-004 Project•PK0-004 Project
Preview 4 out of 159 pages
PK0-004 Project+ BEST STUDY GUIDE 2021/2022A milestone task on the critical path has been completed. 
 
which of the following should the project manager notify? 
 
A owner of predecessor task 
B project team 
C project sponsor 
D project steering committee correct answer- C 
 
During a project assessment, a project manager determines the initial project cost estimates were incorrect oh, and there is not enough budget left, including reserves, to complete the project. 
 
Which of the followi...
A milestone task on the critical path has been completed. 
which of the following should the project manager notify? 
A owner of predecessor task 
B project team 
C project sponsor 
D project steering committee correct answer- C 
During a project assessment, a project manager determines the initial project cost 
estimates were incorrect oh, and there is not enough budget left, including reserves, to 
complete the project. 
Which of the following actions should the project manager take? 
A alert ...
- Exam (elaborations)
- • 155 pages's •
-
PK0-004 Project•PK0-004 Project
Preview 4 out of 155 pages
A milestone task on the critical path has been completed. 
which of the following should the project manager notify? 
A owner of predecessor task 
B project team 
C project sponsor 
D project steering committee correct answer- C 
During a project assessment, a project manager determines the initial project cost 
estimates were incorrect oh, and there is not enough budget left, including reserves, to 
complete the project. 
Which of the following actions should the project manager take? 
A alert ...