Question
1. In a strong matrix structure, employees take daily direction from:
Project manager only
Both, but the project manager has greater influence
Both, but the functional manager has greater influence
Functional manager only
2. If the schedule variance is positive and the cost variance is negative, the project’s status is:
Over budget and behind schedule
Under budget and ahead of schedule
Over budget and ahead of schedule
Under budget and behind schedule
3. Which category of projects wou...