PM 586 Final Exam 2017

PM 586 Final Exam 2017

Here are the best resources to pass PM 586 Final Exam 2017. Find PM 586 Final Exam 2017 study guides, notes, assignments, and much more.

All 1 results

Sort by

PM 586 Final Exam 2017
  • PM 586 Final Exam 2017

  • Exam (elaborations) • 8 pages • 2017
  • PM 586 Final Exam (2017 version) 1. In a strong matrix structure, employees take daily direction from: Project manager only Both, but the project manager has greater influence Both, but the functional manager has greater influence Functional manager only 2. If the schedule variance is positive and the cost variance is negative, the project’s status is: Over budget and behind schedule Under budget and ahead of schedule Over budget and ahead of schedule Under budget and behind schedule 3. Which ...