PM 586 Final Exam 2017
Latest uploads at PM 586 Final Exam 2017. Looking for notes at PM 586 Final Exam 2017? We have lots of notes, study guides and study notes available for your school.
-
1
- 0
- 0
All courses for PM 586 Final Exam 2017
-
PM 586 Final Exam 2017 1
Latest notes & summaries PM 586 Final Exam 2017
PM 586 Final Exam (2017 version)
1. In a strong matrix structure, employees take daily direction from:
Project manager only
Both, but the project manager has greater influence
Both, but the functional manager has greater influence
Functional manager only
2. If the schedule variance is positive and the cost variance is negative, the project’s status is:
Over budget and behind schedule
Under budget and ahead of schedule
Over budget and ahead of schedule
Under budget and behind schedule
3. Which ...
- Exam (elaborations)
- • 8 pages's •
-
PM 586 Final Exam 2017•PM 586 Final Exam 2017
Preview 1 out of 8 pages
PM 586 Final Exam (2017 version)
1. In a strong matrix structure, employees take daily direction from:
Project manager only
Both, but the project manager has greater influence
Both, but the functional manager has greater influence
Functional manager only
2. If the schedule variance is positive and the cost variance is negative, the project’s status is:
Over budget and behind schedule
Under budget and ahead of schedule
Over budget and ahead of schedule
Under budget and behind schedule
3. Which ...