PROJ 592 (PROJ592)

Devry University

Here are the best resources to pass PROJ 592 (PROJ592). Find PROJ 592 (PROJ592) study guides, notes, assignments, and much more.

All 1 results

Sort by

PROJ 592 Week 6 Quiz (Version 1)- Questions and Answers
  • PROJ 592 Week 6 Quiz (Version 1)- Questions and Answers

  • Exam (elaborations) • 8 pages • 2020
  • PROJ 592 Week 6 Quiz (version 1) 1. Question: (TCO E) Using the network below and the additional information provided, find (a) the crash cost per day per activity; (b) which activities should … crashed to meet a project deadline of 12 days at minimum cost; and (c) what the extra cost is to crash the project. Activity Normal Time Crash Time Normal Cost Crash Cost A 5 3 $300 $600 B 3 2 $250 $450 C 6 4 $400 $500 D 5 3 $150 $400 2. Question: (TCO E) The following information is extracted from a...