How much is the hourly tire repair cost if it is estimated that the tire repair is 25% of the tire
depreciation and the life of the tires is 4,000 hours. (See textbook page 48 Example 2.14 for
reference)
Select one:
a. $1.56/hr
b. $6.25/hr
c. $0.10/hr
d. $0.25/hr
a. $1.56/hr
A+ TEST BANK 1
, CM 2113 Wang Test 1 Preparation/CM 2113
Wang Test 1 Practice Exam
Please calculate how many sets of tires are needed during the 10 years' of operation of this
loader assuming one set of tires can be expected to last 4,000 hours, and the loader will be
operated 2,000 hours per year.
Select one:
a. 4 sets
b. 2 sets
c. 3 sets
d. 5 sets
d. 5 sets
Please calculate the hourly tire depreciation cost of the first set of tires considering the time
value of money, assuming that the loader has a service life of 10 years and operates 2,000
hours per year, and a set of tires can be expected to last 4,000 hours. (See textbook page 49
Example 2.14 for reference)
Select one:
a. $6.25/hr
b. $12.5/hr
c. $0.50/hr
d. $2.04/hr
d. $2.04/hr
Please calculate the hourly tire depreciation cost of the second set of tires considering the
time value of money, assuming that the loader has a service life of 10 years and operates
2,000 hours per year, and a set of tires can be expected to last 4,000 hours. (See textbook
page 49 Example 2.14 for reference)
Select one:
a. $5.95/hr
b. $1.68/hr
c. $2.04/hr
A+ TEST BANK 2
, CM 2113 Wang Test 1 Preparation/CM 2113
Wang Test 1 Practice Exam
d. $0.79/hr
b. $1.68/hr
How much is the hourly equipment repair cost if the annual cost of repairs equals 70% of
straight-line depreciation?
Select one:
a. $1.93/hr
b. $3.89/hr
c. $2.75/hr
d. $3.50/hr
a. $1.93/hr
Please calculate the throttle load factor if the engine will work at full throttle while loading the
bucket (45% of the time) and at three-quarter throttle to travel and dump. (See textbook
page 47 Example 2.12 for reference).
Select one:
a. 0.65
b. 0.86
c. 0.45
b. 0.86
Please calculate time factor if it is estimated that the work will be steady at an efficiency equal
to a 55-min hour. (See textbook page 47 Example 2.12 for reference)
Select one:
a. 0.92
b. 0.83
c. 0.75
d. 0.55
a. 0.92
Please calculate the hourly fuel cost if the wheel loader has a 250-fwhp diesel engine, and the
diesel fuel costs $1.20 per gallon, and the operating factor (combined factor) is 0.75. (See
textbook page 47 Example 2.12 for reference)
Select one:
A+ TEST BANK 3