100% tevredenheidsgarantie Direct beschikbaar na je betaling Lees online óf als PDF Geen vaste maandelijkse kosten 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

API 653 RECERTIFICATION EXAM –ACTUAL EXAM-LATEST UPDATE 2025-COMPLETE QUESTIONS WITH CORRECT DETAILED AND VERIFIED ANSWERS | RATED 100% CORRECT!! GUARANTEED PASS!! ALREADY GRADED A+

Beoordeling
-
Verkocht
-
Pagina's
12
Cijfer
A+
Geüpload op
29-07-2025
Geschreven in
2024/2025

API 653 RECERTIFICATION EXAM –ACTUAL EXAM-LATEST UPDATE 2025-COMPLETE QUESTIONS WITH CORRECT DETAILED AND VERIFIED ANSWERS | RATED 100% CORRECT!! GUARANTEED PASS!! ALREADY GRADED A+

Instelling
API 653 RECERTIFICATION
Vak
API 653 RECERTIFICATION









Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
API 653 RECERTIFICATION
Vak
API 653 RECERTIFICATION

Documentinformatie

Geüpload op
29 juli 2025
Aantal pagina's
12
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

API 653 RECERTIFICATION EXAM –ACTUAL EXAM-LATEST UPDATE 2025-
COMPLETE QUESTIONS WITH CORRECT DETAILED AND VERIFIED ANSWERS |
RATED 100% CORRECT!! GUARANTEED PASS!! ALREADY GRADED A+

Per API 653 , with of the following is required when converting an existing tank to operation at
elevated temperatures when it was not originally designed and constructed to API 650, Appendix
M? - (answers)The Shell to bottom joint shall be evaluated for fatigue


When removing an existing tank bottom, all arc-gouged areas of the tank shell-to-bottom shall
be: - (answers)examined using magnetic particle inspection, and defective areas repaired and re-
examined.


If RBI assessment has been conducted and the tank has cathodic protection plus a thin-film
lining, the maximum inspection interval is: - (answers)14 years


When installing a new nozzle in a tank of unknow material, what stress value should be used to
calculate the required shell thickness and reinforcement? - (answers)20,000 lbf/in2


In regards to underside corrosion on tank bottoms, the corrosion rate of steel in a wet
environment. - (answers)may double with every 18 °F increase in temperature above 77 °F.


Grade 350W/50W is acceptable for tank plate to a maximum thickness of: - (answers)45mm
(1.75in) if fully killed and made to a fine grain practice.


If an RBI assessment has been conducted and the tank has a release prevention barrier, the
maximum initial inspection interval is: - (answers)25 years


As an alternative to the procedures in API 653 for the evaluation of any thinning of the tank shell
below minimum required wall thickness may be evaluated for continued service using which
code? - (answers)API RP 579, section 4, 5 or 6.


When welding on a tank shell constructed of Group I steel that is greater than 1.5 inches thick
below what minimum metal temperature ?preheat? - (answers)200°F

, When evaluated an existing temperature services tank, which has a successful service history of
operation but was not originally designed and constructed to the requirement of API 650,
appendix M, which condition temperature has to be used? - (answers)The max Operating
Temperature shall not exceed the temperature at which the tank has successfully operated in the
pass.


Flange material used for tank repair and alteration shall meet the minimum requirements for the
material specifications according to: - (answers)The as built standard


which is an advantage of thick film UN-REINFORCED linings ? - (answers)Fast curing and can
be put back in service after 24 hours at normal ambient temperature.


The perimeter welds on a welded-on patch plate in the critical zone should be ? - (answers)Two-
pass and examined visually and by either MP or PT.


Existent welds on a tank shell are found to e closer than allowed by API 650 (7th Edition). Under
what conditions can these welds be considered to be acceptable for continued service? -
(answers)Examined by MP inspection with no rejectable indications.


The requirements of which standard shall be considered in the evaluation and alteration to the
tank roof and roof-to-shell junction ? - (answers)Current applicable standard


Welding procedure for ladder and platform assemblies, but not their attachment to the tank? -
(answers)Shall comply with either AWS D1.1, AWS D1.6 or ASME Code Section IX.


In floating roof tanks, shell nozzles without internal piping within operating range of the floating
roof shall be supplied? - (answers)Flush on the inside of the tank.


The attachment welds of new lap-welded shell patch plates shall be examined by: -
(answers)Visually and by either MP or PT

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
SmarttDocs Havard School
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
121
Lid sinds
11 maanden
Aantal volgers
5
Documenten
1243
Laatst verkocht
3 weken geleden
SMARTDOCS

Welcome to Smartdocs– your go-to source for high-quality study guides, question banks, and exam-focused materials for every subject and level. Whether you're cramming for a last-minute test or aiming for top marks, our clear, accurate, and easy-to-use documents are designed to help you succeed faster. Trusted by students, built for results – level up your learning today!

4,9

39 beoordelingen

5
36
4
2
3
1
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen