DBIA: PRINCIPLES OF DESIGN-BUILD
AND POST AWARD & CONTRACTS.
EXAM QUESTIONS AND ANSWERS 100%
PASS
Miller Act 1935 - ANS Federal Government passed bond requiring payment and performance
bonds on all public works, what year?
Brooks Bill 1972 - ANS Bill directing A/E's selected on qualifications, what year?
Clinger Cohen Act/Defense Procurement Reform Act 1996 - ANS Allows all federal agencies to
utilize Design-Build. Prior to that no enabling legislation existed allowing Design-Build.
Standard of Care - ANS The level of quality that any average Design Professional would be
able to perform given the circumstances.
Design Bid Build - ANS Slowest Project Delivery method, linear in nature, prescriptive (owner
knows what they want),
Multi Prime - ANS Project Delivery - Many contracts through Owner
CM at Risk - ANS Project Delivery method allowing the contractor to come on board very
early in design for preconstruction services yet maintains separation between Designer and
Builder contractually.
1 @COPYRIGHT 2025/2026 ALLRIGHTS RESERVED.
, Design Build - ANS Fastest Project Delivery method, fast tracking possible overlapping design
with construction utilizing incremental packages.
Low Bid - ANS Procurement Method - Most Familiar
Negotiated (Qualifications Based) - ANS Procurement Method - Common for A/E
Best Value - ANS Procurement Method - Qualifications and Price
Sole Source - ANS Procurement Method - Direct
Lump Sum - ANS Contract Format w/ agreed upon fixed price
Cost Plus Fee - ANS Contract Format - contractor reimbursed for actual cost plus an agreed
upon percentage
GMP (Guaranteed Maximum Price) - ANS Contract Format - Combines Cost-Plus & Lump-
Sum, contractor reimbursed for actual cost plus a fee only up to a certain amount.
Unit Price - ANS Contract Format - cost per piece
Target Price - ANS Contract Format - established cost/benchmark determined jointly by
project team.
Trust, Flexibility - ANS Successful Design Build requires _____ & _______ between
participants
Hammurabi - ANS Singular responsibility for both design & construction was first codified by
____
2 @COPYRIGHT 2025/2026 ALLRIGHTS RESERVED.
AND POST AWARD & CONTRACTS.
EXAM QUESTIONS AND ANSWERS 100%
PASS
Miller Act 1935 - ANS Federal Government passed bond requiring payment and performance
bonds on all public works, what year?
Brooks Bill 1972 - ANS Bill directing A/E's selected on qualifications, what year?
Clinger Cohen Act/Defense Procurement Reform Act 1996 - ANS Allows all federal agencies to
utilize Design-Build. Prior to that no enabling legislation existed allowing Design-Build.
Standard of Care - ANS The level of quality that any average Design Professional would be
able to perform given the circumstances.
Design Bid Build - ANS Slowest Project Delivery method, linear in nature, prescriptive (owner
knows what they want),
Multi Prime - ANS Project Delivery - Many contracts through Owner
CM at Risk - ANS Project Delivery method allowing the contractor to come on board very
early in design for preconstruction services yet maintains separation between Designer and
Builder contractually.
1 @COPYRIGHT 2025/2026 ALLRIGHTS RESERVED.
, Design Build - ANS Fastest Project Delivery method, fast tracking possible overlapping design
with construction utilizing incremental packages.
Low Bid - ANS Procurement Method - Most Familiar
Negotiated (Qualifications Based) - ANS Procurement Method - Common for A/E
Best Value - ANS Procurement Method - Qualifications and Price
Sole Source - ANS Procurement Method - Direct
Lump Sum - ANS Contract Format w/ agreed upon fixed price
Cost Plus Fee - ANS Contract Format - contractor reimbursed for actual cost plus an agreed
upon percentage
GMP (Guaranteed Maximum Price) - ANS Contract Format - Combines Cost-Plus & Lump-
Sum, contractor reimbursed for actual cost plus a fee only up to a certain amount.
Unit Price - ANS Contract Format - cost per piece
Target Price - ANS Contract Format - established cost/benchmark determined jointly by
project team.
Trust, Flexibility - ANS Successful Design Build requires _____ & _______ between
participants
Hammurabi - ANS Singular responsibility for both design & construction was first codified by
____