Garantie de satisfaction à 100% Disponible immédiatement après paiement En ligne et en PDF Tu n'es attaché à rien 4,6 TrustPilot
logo-home
Examen

CEE 4100 EXAM REVIEW QUESTIONS

Note
-
Vendu
-
Pages
8
Grade
A+
Publié le
05-11-2025
Écrit en
2025/2026

CEE 4100 EXAM REVIEW QUESTIONS

Établissement
CEE 4100
Cours
CEE 4100









Oups ! Impossible de charger votre document. Réessayez ou contactez le support.

École, étude et sujet

Établissement
CEE 4100
Cours
CEE 4100

Infos sur le Document

Publié le
5 novembre 2025
Nombre de pages
8
Écrit en
2025/2026
Type
Examen
Contient
Questions et réponses

Sujets

Aperçu du contenu

CEE 4100 EXAM REVIEW QUESTIONS


What format is used for cost estimation - Answer -Construction Specifications Institue
(csi)

Why CSI format? - Answer -16 major divisions
grouped by building trades and broad scope sections
industry standard for cataloguing info

Main variables for Unit Price Estimating - Answer -- Unit price cost
- Construction equipment rental cost
- Crew listing
- Historical cost index
- City cost index
- Location factor
-Overhead and profit

2 Construction Cost Indices - Answer -Construction Cost Index (CCI)
Building Cost Index (BCI)

Labor Productivity Rate - Answer -Work per unit time or other unit

Quantity takeoff - Answer -required number of units including waste

Work hours required - Answer -Productivity rate (work hours per unit) x quantity takeoff

Duration - Answer -work hours required per crew size

Activity labor cost - Answer -duration x hourly crew labor cost

Steps to prepare a detailed estimate - Answer -1. scope of work
2. materials quantity takeoff
3. cost of materials
4. cost of labor
5. cost of owned and rented equipment
6. cost of specialty work
7. taxes, bonds, insurance
8. project contingency
9. determine reasonable profit

Total direct costs - Answer -multiply quantities of each of the components by material,
labor and equipment unit costs

, Type of summary sheets - Answer -Lump-sum bid
Unit price bid

Lump sum bid - Answer --quantity survey totals and their units
-material unit prices and extensions
-labor unit prices and extensions
-equipment costs for entire project computed separately

UNIT Price Bid - Answer --one summary sheet per pay item
-each summary sheet includes several different work categories
-columns for materials labor, equipment, and subcontracts

Why recap sheets - Answer -- organization
- summarize entire project on single sheet
- allows for easy adjustments

What does unbalanced bidding apply to? - Answer -unit bidding

What is front end loading - Answer -Raises prices for items that occur early in the
project and reduces prices for pay items that occur later in the project

What does unbalanced bidding allow for - Answer -taking advantage of expected
mistakes in owners (engineers) estimate

Disadvantages of unbalanced bidding - Answer --changes can have an unrealistic
impact on the pricing
-Unrealistic unit prices can adversely affect the owner's or A/E's decision
- bid can be rejected if thought to be unfair or unresponsive

Direct cost - Answer --can be assigned directly to work items -cause and effect
relationship
-disappears if a work item is eliminated

Indirect cost - Answer --can be assigned indirectly to work items
-remains if a work item is eliminated

Direct cost examples - Answer -Basic wages

Indirect cost examples - Answer --taxes and insurance
-social security
health and welfare funds

Owning costs - Answer --Depreciation
-interest
-insurance
-taxes
€12,18
Accéder à l'intégralité du document:

Garantie de satisfaction à 100%
Disponible immédiatement après paiement
En ligne et en PDF
Tu n'es attaché à rien

Faites connaissance avec le vendeur

Seller avatar
Les scores de réputation sont basés sur le nombre de documents qu'un vendeur a vendus contre paiement ainsi que sur les avis qu'il a reçu pour ces documents. Il y a trois niveaux: Bronze, Argent et Or. Plus la réputation est bonne, plus vous pouvez faire confiance sur la qualité du travail des vendeurs.
GEEKA YALA UNIVERSITY
S'abonner Vous devez être connecté afin de suivre les étudiants ou les cours
Vendu
2011
Membre depuis
3 année
Nombre de followers
1447
Documents
48584
Dernière vente
2 heures de cela

3,8

345 revues

5
172
4
61
3
44
2
16
1
52

Récemment consulté par vous

Pourquoi les étudiants choisissent Stuvia

Créé par d'autres étudiants, vérifié par les avis

Une qualité sur laquelle compter : rédigé par des étudiants qui ont réussi et évalué par d'autres qui ont utilisé ce document.

Le document ne convient pas ? Choisis un autre document

Aucun souci ! Tu peux sélectionner directement un autre document qui correspond mieux à ce que tu cherches.

Paye comme tu veux, apprends aussitôt

Aucun abonnement, aucun engagement. Paye selon tes habitudes par carte de crédit et télécharge ton document PDF instantanément.

Student with book image

“Acheté, téléchargé et réussi. C'est aussi simple que ça.”

Alisha Student

Foire aux questions