Exam / Virginia DEQ SWM Plan Reviewer Certification
Preparation/Virginia DEQ SWM Plan Reviewer
Certification Practice Exam With Complete Questions And
Correct Answers| Brand New Version!
The Virginia Stormwater Management Program is authorized by the ______ and
administered through the ______ - ans -Virginia Stormwater Management Act,
Virginia Stormwater Management Program Regulation
VPDES Permit/Construction GP authorizes discharge of stormwater from
construction activities that are - ans -greater than or equal to an acre
The Stormwater Management Act requires the State Water Control Board to - ans
-permit, regulate, and control stormwater runoff
DEQ has ___ days to complete review of real or potential inter-jurisdictional
impacts upon request - ans -90
The Stormwater Management Act requires the following individuals to obtain and
maintain a certificate of competency - ans -staff of a stormwater program, anyone
contracted by a VSMP authority, standard and specification holders
The dual certificate will expire three years from - ans -the latest date of the
certificates
SWM plan must be approved by ___ before land disturbance - ans -VSMP
program authority
The water quality criteria sets a site-based load limit of ____ of total phosphorus
for new development - ans -0.41 lbs/acre/year
The phosphorus load limit uses the - ans -10% impervious cover
Part II B and II C water quantity criteria addresses - ans -channel protection and
flood protection
, The operator must submit the DEQ Notice of Termination form to the VSMP
authority - ans -within 30 days of meeting one or more of the following conditions
When is permanent vegetation considered established? - ans -uniform, mature
enough to survive, will inhibit erosion
Record drawings must be sealed and signed by a - ans -professional registered in
VA
Within ___ days of completing the requirements of the permit conditions, the
locality VSMP authority must return or terminate any bonds or securities provided
by the operator - ans -60
What legal agreement provides a VSMP inspector access to property for
conducting post-construction regulatory inspections? - ans -long-term
maintenance agreement
VSMP authorities or its designee must perform post construction inspections
every - ans -5 years
If a recorded long-term maintenance agreement is not required then the facility is
- ans -not subject to the VSMP authority post construction inspection
requirements
At a minimum, a stormwater management facility shall be inspected by the
responsible state agency on an - ans -annual basis and after any storm that causes
the capacity of the facility's principal spillway to be exceeded
Review of any plan previously disapproved shall be reviewed within _____ by the
VSPM authority - ans -45 days
A simple rooftop disconnect is not advisable for residential lots less than - ans -
6,000 ft^2
Max impervious rooftop area treated; 1,000 ft^2 per simple disconnection and
longest flow path is - ans -75 ft