2) Questions with Accurate
Answers
A business scenario is a description of a business situation or problem
that describes what 3 things? correct answer past events that are
relevant
current key information
expected or desired outcomes
A Gantt chart is an example of a __________ tool.
Collaboration
Scheduling correct answer Scheduling
Correct! Project managers use Gantt charts in the process of
scheduling.
A project is successful if it meets the triple constraints of what 3 things?
correct answer scope, schedule, and budget
A project is successful if it meets What triple constraints? correct
answer 1. the project delivered what was specified in the project scope
,2. The project was within the allotted amount of time
3. The Project was for the specified funding
According to OPM3, what takes place during the fifth and final level of
project management maturity?
Technologies and reporting are sporadic.
Metrics are put in place to collect performance data.
Lessons and best practices are applied correct answer Lessons and best
practices are applied.
Correct! The lessons learned and best practices are applied in the fifth
and final level of project management maturity.
Define Operations correct answer the ongoing, daily activities of an
organization that produce revenue and expense
Define program. correct answer a group of initiatives that support the
long-term goals and objectives of the company; it may be established
and is a group of related projects
,Define project? correct answer a temporary endeavor with a specified
start and end date
Google Drive is an example of what?
A scheduling tool
A social networking site
A collaboration site
Certification platform correct answer A collaboration site
Correct! Google Drive is a work collaboration site
In addition to the triple constraints, what other considerations may
determine if the project is successful?
A. The project is a project of high interest to the CEO.
, B. There are no government regulations that affect the product of the
project.
C. The requirements in the scope adequately define the project's
objectives. correct answer C. The requirements in the scope adequately
define the project's objectives.
Correct! The scope requirements should adequately define project
objectives
In which way can conflict be an opportunity for a project?
It can reveal something critical about the project.
It can help to establish expectations.
It can assure aggressive deliverable schedules. correct answer It can
reveal something critical about the project.
Correct! Conflict can teach the project manager and team members
something critical about the project that was not previously known.
One of the project manager's tools for communicating is the 8 and 80
Rule. What does the number 80 refer to in this rule?