Reducing the set-up time does which of the following? Correct Answer-
a.
Reduces the cost of each part.
b.
Minimizes waste.
c.
Reduces the time required to manufacture a specific number of parts.
d.
All responses are correct. (Answer)
e.
Reduces cost and improves quality.
Poka-Yoke: Correct Answer-Select one:
a.
Makes material handling easier.
b.
Uses the Theory of Constraints to smooth production.
c.
Mistake-proofs a process. (Answer)
d.
Enables data sharing of key processes.
,Benefits of Failure Modes and Effects Analysis (FMEA) include:
Correct Answer-a.
An effective method for evaluating the effect of proposed changes to the
design and/or operational procedures on mission success and safety.
b.
All responses are correct. (Answer)
c.
Provides a documented uniform method of assessing potential failure
mechanisms, failure modes and their impact on system operation.
d.
Providing a documented method for selecting a design with a high
probability of successful operation and safety.
While philosophies vary the common threads regarding Six Sigma
include: Correct Answer-Select one:
a.
A continual effort to reduce variation in all processes within the
organization.
b.
A management environment that supports these initiatives as a business
strategy.
c.
,Use of teams that are assigned well-defined projects that have direct
impact on the organization's bottom line.
d.
All responses are correct. (Answer)
e.
Use of teams that are assigned well-defined projects that have direct
impact on the organization's bottom line and continual effort to reduce
variation.
Consider the Failure Mode and Effects Analysis presented below for
patient health. Which action(s) below are the best: Correct Answer-a.
Pursue Access to Patient Health Records first.
b.
Take no action.
c.
In order, tackle: 1) Access to Patient Health Records, 2) Triage (in-
person or virtual appointment), 3) Patient Health Screening.
d.
Work first on Patient Health Screening. (Answer)
Using the Theory of Constraints which conclusion is correct for the
production system pictures below? Correct Answer-a.
This production system is well balanced and optimized.
, b.
Machine 4 is the weakest link with the slowest production rate.
c.
Machine 2 can likely be removed due to its moderate work in process.
d.
Machine 3 is the weakest link with the slowest production rate.
(Answer)
Modern cost of quality curves (compared to traditional cost of quality
curves): Correct Answer-Select one:
a.
Has a higher cost of nonconformance
b.
Are no different.
c.
Has a lower cost of nonconformance.
d.