Well-blasted rock has a swell percentage of: (Principles and Practices of Commercial Construction -- Earthwork) - ANSWER20% Lifelines in areas subjected to cutting or abrasion shall be a minimum of ______ inch wire core manila rope (OSHA) - ANSWER7/8 All excavations made in Type B soil 20 feet or less in depth which have vertically sided lower portions shall be shielded or supported to a height _____ inches above the top of the vertical side (OSHA) - ANSWERAt least 18 inches The calculated fire-resistance rating for a 3.8 inch thick sand and light weight aggregate precast concrete wall shall be _______ hour(s). (Florida Building Code -- Calculated Fire Resistance) - ANSWER2 hours Welded splices are almost always necessary in_______. (Reinforcing Bars -- Welding) - ANSWERPrecast Concrete Construction 6. The OSHA area office has a maximum of ____ days to assess the penalty for failure to abate a violation.

Montrer plus Lire moins
Établissement
Florida GC
Cours
Florida GC

Aperçu du contenu

Florida GC Exam - Project Management
Section(100% Correct)

Well-blasted rock has a swell percentage of:

(Principles and Practices of Commercial Construction --> Earthwork) - ANSWER20%

Lifelines in areas subjected to cutting or abrasion shall be a minimum of ______ inch wire core
manila rope

(OSHA) - ANSWER7/8

All excavations made in Type B soil 20 feet or less in depth which have vertically sided lower portions
shall be shielded or supported to a height _____ inches above the top of the vertical side

(OSHA) - ANSWERAt least 18 inches

The calculated fire-resistance rating for a 3.8 inch thick sand and light weight aggregate precast
concrete wall shall be _______ hour(s).

(Florida Building Code --> Calculated Fire Resistance) - ANSWER2 hours

Welded splices are almost always necessary in_______.

(Reinforcing Bars --> Welding) - ANSWERPrecast Concrete Construction

6. The OSHA area office has a maximum of ____ days to assess the penalty for failure to abate a
violation.

(Florida Contractors Manual --> Categories of Violations) - ANSWER30 Days

7. High-density R-30 batts used in cathedral ceilings are_____ inches thick.

(Energy Efficient Building Construction --> Cathedral Ceilings) - ANSWER8 - 1/4

8. According to ASTM C94, when truck mixers are used the load must be completely discharged
within______ after batching.

(Design and Control of Concrete Mixtures --> Mixing Concrete) - ANSWER90 Minutes

9. Floor landings in stairways shall be installed at intervals not to exceed_______.

(Florida Building Code --> Stairway Construction, Landings) - ANSWER12' Vertically

10. The thickness of concrete floor slabs supported directly on the ground shall not be less than____
inches.

(Florida Building Code --> Concrete, Slab, Minimum) - ANSWER3 - 1/2

11. In _______ , the tendons are raised higher above the forms in the vicinity of the supporting
column than at the midspan of the slab.

, (Principles and Practices of Commercial Construction --> Tendon, Post Tensioning) - ANSWERPost-
tensioned Concrete Slabs

12. The maximum permissible slope for access aisles serving accessible parking spaces shall not be
greater than_______.

(Accessibility) - ANSWER1:48

13. Excavations located five feet or less from the lot line during the renovation of an existing building,
shall be enclosed with a barrier not less than____ feet high.

(Florida Building Code --> Barriers, Protection) - ANSWER6'

14. The preliminary site investigation is usually done _______.

(Principles and Practices of Commercial Construction --> Preliminary Investigation) - ANSWERIn two
stages

15. Where permitted, spiral stairways shall be constructed in such a way that the risers shall be
sufficient to provide a headroom of _____ minimum.

(Florida Building Code --> Spiral Stairs, Construction) - ANSWER6' - 6"

16. Whenever materials are dropped________ to any point outside the exterior walls of the building,
an enclosed chute shall be used.

(OSHA --> Chutes) - ANSWERMore than 20'

17. Automatic sprinkler systems in residential structures up to and including four stories in height
shall be permitted to be installed in accordance with ______.

(Florida Building Code --> Automatic Sprinkler Systems) - ANSWERNFPA 13-47R

18. Masonry cements consist of portland cement together with other materials to enhance all of the
following except ______.

(Design and Control of Concrete Mixtures --> Masonry Cement) - ANSWERAir-Entrainment

19. In steel frame construction, cross-bracing loads are typically_______.

(Principles and Practices of Commercial Construction --> Cross Bracing, Structural Steel) - ANSWERIn
Tension

20. Barricades for protection of employees shall conform to_______.

(OSHA --> Barricades) - ANSWERThe Manual on Uniform Traffic Control Devices

21. The minimum dimensions for a crawl space access opening in a building shall be not less than
_____ inches.

(Florida Building Code --> Crawl Space, Access) - ANSWER18" x 24"

22. A _____ truss develops movement at its bearing points when under load.

(Walker's Building Estimator's Reference Book --> Trusses, Wood Roof) - ANSWERScissor

23. When gypsum materials are being mixed or used for joint treatment or laminating, the room
temperature shall be maintained at not less than 500 F for not less than ______ hours before use.

École, étude et sujet

Établissement
Florida GC
Cours
Florida GC

Infos sur le Document

Publié le
16 octobre 2024
Nombre de pages
8
Écrit en
2024/2025
Type
Examen
Contient
Questions et réponses

Sujets

€13,86
Accéder à l'intégralité du document:

Mauvais document ? Échangez-le gratuitement Dans les 14 jours suivant votre achat et avant le téléchargement, vous pouvez choisir un autre document. Vous pouvez simplement dépenser le montant à nouveau.
Rédigé par des étudiants ayant réussi
Disponible immédiatement après paiement
Lire en ligne ou en PDF

Faites connaissance avec le vendeur

Seller avatar
Les scores de réputation sont basés sur le nombre de documents qu'un vendeur a vendus contre paiement ainsi que sur les avis qu'il a reçu pour ces documents. Il y a trois niveaux: Bronze, Argent et Or. Plus la réputation est bonne, plus vous pouvez faire confiance sur la qualité du travail des vendeurs.
Papersbylee Chowan University
S'abonner Vous devez être connecté afin de suivre les étudiants ou les cours
Vendu
22
Membre depuis
2 année
Nombre de followers
14
Documents
1264
Dernière vente
6 mois de cela

3,3

7 revues

5
1
4
1
3
4
2
1
1
0

Documents populaires

Récemment consulté par vous

Pourquoi les étudiants choisissent Stuvia

Créé par d'autres étudiants, vérifié par les avis

Une qualité sur laquelle compter : rédigé par des étudiants qui ont réussi et évalué par d'autres qui ont utilisé ce document.

Le document ne convient pas ? Choisis un autre document

Aucun souci ! Tu peux sélectionner directement un autre document qui correspond mieux à ce que tu cherches.

Paye comme tu veux, apprends aussitôt

Aucun abonnement, aucun engagement. Paye selon tes habitudes par carte de crédit et télécharge ton document PDF instantanément.

Student with book image

“Acheté, téléchargé et réussi. C'est aussi simple que ça.”

Alisha Student

Foire aux questions