PMP Exam Prep - Communications Management CORRECT 100%

Note
-
Vendu
-
Pages
12
Grade
A+
Publié le
07-10-2024
Écrit en
2024/2025

What is especially important when the project manager is working with virtual team leads? - Regulating nonverbal communications to maintain cross-cultural respect - Asking for acknowledgment to ensure that the message was understood as intended - Getting feedback to ensure that the intended message is being received - Using an appropriate level of formality for these horizontal communications - ANSWER Getting feedback to ensure that the intended message is being received What is an enterprise environmental factor (EEF) that could affect whether a project can take advantage of a system to produce automated transcripts of virtual meetings? - Whether meetings are scheduled or impromptu

Montrer plus Lire moins
Établissement
PMP
Cours
PMP









Oups ! Impossible de charger votre document. Réessayez ou contactez le support.

École, étude et sujet

Établissement
PMP
Cours
PMP

Infos sur le Document

Publié le
7 octobre 2024
Nombre de pages
12
Écrit en
2024/2025
Type
Examen
Contient
Questions et réponses

Sujets

Aperçu du contenu

PMP Exam Prep - Communications
Management CORRECT 100%

What is especially important when the project manager is working with virtual team leads?

- Regulating nonverbal communications to maintain cross-cultural respect

- Asking for acknowledgment to ensure that the message was understood as intended

- Getting feedback to ensure that the intended message is being received

- Using an appropriate level of formality for these horizontal communications - ANSWER Getting
feedback to ensure that the intended message is being received



What is an enterprise environmental factor (EEF) that could affect whether a project can take advantage
of a system to produce automated transcripts of virtual meetings?

- Whether meetings are scheduled or impromptu

- Required meeting minutes format

- Meeting record keeping policy

- Languages spoken - ANSWER Languages spoken



When a team member responsible for an activity reiterates what needs to be done and there is an
obvious flaw in his or her understanding, what is a likely result if the receiver corrects this error?

- The flaw will be resolved without schedule risk or residual risk.

- The flaw will be resolved without schedule risk, but residual risk remains unless there is another round
of communications.

- Correcting the flaw will impact the schedule and create residual risk.

- Correcting the flaw will impact the schedule, but there will be no residual risk since the
communications were successful. - ANSWER The flaw will be resolved without schedule risk, but residual
risk remains unless there is another round of communications.



What is an example of an enterprise environmental factor (EEF) that might be used as an input to the
Plan Communications Management process?

- Communication methods

, - Communication models

- Communication technology rates

- Lessons learned about communication - ANSWER Communication technology rates



What might prevent a project manager from fully adopting a new conversation thread tracking system to
replace e-mails?

- Unlike e-mail, the system would create too many communication channels.

- IT requires that all project communications be documented and traceable.

- The medium isn't formal enough for certain communications.

- A key stakeholder didn't make it through the training for the system. - ANSWER A key stakeholder didn't
make it through the training for the system.



What is the most important communication dimension for a project manager when handling conflict
resolution with a customer who thought a team lead was rude?

- Horizontal

- Formal

- Official

- External - ANSWER Formal



What is an example of noise in a communication?

- Expert using technical jargon

- Receiver indicating that the message was received without indicating understanding

- Sender having to repeat a message in a different manner

- New video chat technology - ANSWER Expert using technical jargon



A project is complex, and team roles vary considerably. Some team members have complained during
their project performance appraisals that they missed a key metric because the team reports were too
detailed. What can the project manager provide to resolve this situation?

- Dashboards

- Graphics and visual aids to existing reports
€10,17
Accéder à l'intégralité du document:

Garantie de satisfaction à 100%
Disponible immédiatement après paiement
En ligne et en PDF
Tu n'es attaché à rien


Document également disponible en groupe

Faites connaissance avec le vendeur

Seller avatar
Les scores de réputation sont basés sur le nombre de documents qu'un vendeur a vendus contre paiement ainsi que sur les avis qu'il a reçu pour ces documents. Il y a trois niveaux: Bronze, Argent et Or. Plus la réputation est bonne, plus vous pouvez faire confiance sur la qualité du travail des vendeurs.
Lecchris West Virgina University
S'abonner Vous devez être connecté afin de suivre les étudiants ou les cours
Vendu
40
Membre depuis
2 année
Nombre de followers
15
Documents
3203
Dernière vente
1 mois de cela
LECCHRIS

3,8

6 revues

5
2
4
1
3
3
2
0
1
0

Récemment consulté par vous

Pourquoi les étudiants choisissent Stuvia

Créé par d'autres étudiants, vérifié par les avis

Une qualité sur laquelle compter : rédigé par des étudiants qui ont réussi et évalué par d'autres qui ont utilisé ce document.

Le document ne convient pas ? Choisis un autre document

Aucun souci ! Tu peux sélectionner directement un autre document qui correspond mieux à ce que tu cherches.

Paye comme tu veux, apprends aussitôt

Aucun abonnement, aucun engagement. Paye selon tes habitudes par carte de crédit et télécharge ton document PDF instantanément.

Student with book image

“Acheté, téléchargé et réussi. C'est aussi simple que ça.”

Alisha Student

Foire aux questions