Garantie de satisfaction à 100% Disponible immédiatement après paiement En ligne et en PDF Tu n'es attaché à rien 4.2 TrustPilot
logo-home
Examen

Unit 4 Boiler Operation Exam Questions And Answers 100% Correct

Note
-
Vendu
-
Pages
5
Grade
A+
Publié le
27-09-2024
Écrit en
2024/2025

Unit 4 Boiler Operation Exam Questions And Answers 100% CorrectUnit 4 Boiler Operation Exam Questions And Answers 100% CorrectUnit 4 Boiler Operation Exam Questions And Answers 100% CorrectUnit 4 Boiler Operation Exam Questions And Answers 100% Correct When should wet layup be used? Select one: a. When a boiler may be exposed to freezing conditions. b. When a boiler is on standby. c. For long term storage. d. When desiccant is unavailable. - ANSWER-b In a multiple boiler high pressure steam plant, when starting an entire system from cold Select one:

Montrer plus Lire moins
Établissement
Unit 4 Boiler Operation
Cours
Unit 4 Boiler Operation









Oups ! Impossible de charger votre document. Réessayez ou contactez le support.

École, étude et sujet

Établissement
Unit 4 Boiler Operation
Cours
Unit 4 Boiler Operation

Infos sur le Document

Publié le
27 septembre 2024
Nombre de pages
5
Écrit en
2024/2025
Type
Examen
Contient
Questions et réponses

Sujets

Aperçu du contenu

Unit 4 Boiler Operation Exam
Questions And Answers 100%
Correct
When should wet layup be used?
Select one:
a. When a boiler may be exposed to freezing conditions.
b. When a boiler is on standby.
c. For long term storage.
d. When desiccant is unavailable. - ANSWER-b


In a multiple boiler high pressure steam plant, when starting an entire system from
cold
Select one:
a. A small auxiliary heating boiler is used to warm the steam lines while the power
boilers are warming.
b. All the boilers are started and warmed at the same time.
c. The entire system warms and pressurizes as one boiler warms, except for the
boilers being left off line.
d. Boilers remaining off-line must have their boiler and header stop valves open,
and their non-return drain valves shut. - ANSWER-c


Although boilers have many different ignition systems, they all follow the same
sequence of steps. Which of the following is the third step?
Select one:
a. Main burner ignition
b. Pilot ignition
c. Post Purge
d. Pre-purge - ANSWER-a

, How often should the low water cut-off of a low pressure steam heating boiler be
blown off?
Select one:
a. Daily
b. Monthly
c. Twice per shift
d. Weekly - ANSWER-a


Deaerators often have low-level alarms and low-low level trips
Select one:
a. in case the boiler trips.
b. in case the boiler feedwater pumps trip.
c. in case the boiler feedwater valve fails open.
d. in case the condensate transfer pumps trip. - ANSWER-d


A well-planned PM system will
Select one:
a. ensure equipment longevity.
b. create less need for rounds and inspections.
c. will cover only the most critical plant equipment.
d. respond quickly to equipment breakdown. - ANSWER-a


When preparing to start a steam boiler with a fully modulating firing rate control,
set the manual-automatic switch to _________ and the flame control switch to the
__________ position.
Select one:
a. automatic, low-fire
b. manual, low-fire
c. manual, high-fire
d. manual, automatic - ANSWER-b
€11,05
Accéder à l'intégralité du document:

Garantie de satisfaction à 100%
Disponible immédiatement après paiement
En ligne et en PDF
Tu n'es attaché à rien


Document également disponible en groupe

Faites connaissance avec le vendeur

Seller avatar
Les scores de réputation sont basés sur le nombre de documents qu'un vendeur a vendus contre paiement ainsi que sur les avis qu'il a reçu pour ces documents. Il y a trois niveaux: Bronze, Argent et Or. Plus la réputation est bonne, plus vous pouvez faire confiance sur la qualité du travail des vendeurs.
NursingTutor1 West Virginia University
S'abonner Vous devez être connecté afin de suivre les étudiants ou les cours
Vendu
1633
Membre depuis
2 année
Nombre de followers
1073
Documents
18045
Dernière vente
2 jours de cela
Nursing Tutor

Paper Due? Worry not. Hello. Welcome to NursingTutor. Here you\'ll find verified study materials for your assignments, exams and general school work. All papers here are graded A to help you get the best grade. Also, I am a friendly person so, do not hesitate to send a message in case you have a query. I wish you Luck.

3,9

447 revues

5
212
4
76
3
89
2
21
1
49

Pourquoi les étudiants choisissent Stuvia

Créé par d'autres étudiants, vérifié par les avis

Une qualité sur laquelle compter : rédigé par des étudiants qui ont réussi et évalué par d'autres qui ont utilisé ce document.

Le document ne convient pas ? Choisis un autre document

Aucun souci ! Tu peux sélectionner directement un autre document qui correspond mieux à ce que tu cherches.

Paye comme tu veux, apprends aussitôt

Aucun abonnement, aucun engagement. Paye selon tes habitudes par carte de crédit et télécharge ton document PDF instantanément.

Student with book image

“Acheté, téléchargé et réussi. C'est aussi simple que ça.”

Alisha Student

Foire aux questions