Garantie de satisfaction à 100% Disponible immédiatement après paiement En ligne et en PDF Tu n'es attaché à rien 4.2 TrustPilot
logo-home
Examen

SCMA 331 FINAL CH 13 UPDATED Exam Questions and CORRECT Answers

Note
-
Vendu
-
Pages
20
Grade
A+
Publié le
15-09-2024
Écrit en
2024/2025

SCMA 331 FINAL CH 13 UPDATED Exam Questions and CORRECT Answers Plans for new product development generally fall within the scope of aggregate planning. - CORRECT ANSWER- False The aggregate planning process usually includes dispatching of individual jobs. - CORRECT ANSWER- False Frito-Lay uses aggregate planning to match capacity with demand because of the ________ associated with its specialized processes. A) high variable cost and high fixed cost B) high variable cost and low fixed cost C) low variable cost and high fixed cost D) low variable cost and low fixed cost E) none of the above - CORRECT ANSWER- C

Montrer plus Lire moins
Établissement
SCMA 331
Cours
SCMA 331










Oups ! Impossible de charger votre document. Réessayez ou contactez le support.

École, étude et sujet

Établissement
SCMA 331
Cours
SCMA 331

Infos sur le Document

Publié le
15 septembre 2024
Nombre de pages
20
Écrit en
2024/2025
Type
Examen
Contient
Questions et réponses

Sujets

Aperçu du contenu

SCMA 331 FINAL CH 13 UPDATED Exam
Questions and CORRECT Answers
Plans for new product development generally fall within the scope of aggregate planning. -
CORRECT ANSWER- ✔✔False


The aggregate planning process usually includes dispatching of individual jobs. - CORRECT
ANSWER- ✔✔False


Frito-Lay uses aggregate planning to match capacity with demand because of the ________
associated with its specialized processes.
A) high variable cost and high fixed cost
B) high variable cost and low fixed cost
C) low variable cost and high fixed cost
D) low variable cost and low fixed cost

E) none of the above - CORRECT ANSWER- ✔✔C


Under which of the following do planning tasks associated with job assignments, ordering,
job scheduling, and dispatching typically fall?
A) short-range plans
B) intermediate-range plans
C) long-range plans
D) mission-related planning

E) strategic planning - CORRECT ANSWER- ✔✔A


Under which of the following do planning tasks associated with production planning and
budgeting, as well as setting employment, inventory, and subcontracting levels, typically fall?
A) short-range plans
B) intermediate-range plans
C) long-range plans
D) demand options

E) strategic planning - CORRECT ANSWER- ✔✔B

,Top executives tend to focus their attention on which type of forecasts?
A) short-range
B) intermediate-range
C) long-range
D) weather

E) the forecast for the next day's absentee levels - CORRECT ANSWER- ✔✔C


Which of the following would most likely fall under the scope of only an operations
manager?
A) research and development
B) new product plans
C) capital investments
D) facility location/capacity

E) setting inventory levels - CORRECT ANSWER- ✔✔E


Aggregate planning occurs over the medium or intermediate future of 3 to 18 months. -
CORRECT ANSWER- ✔✔True


Aggregate planning in manufacturing ties organizational strategic goals to a production plan.
- CORRECT ANSWER- ✔✔True


One of the four things needed for aggregate planning is a logical overall unit for measuring
sales and output. - CORRECT ANSWER- ✔✔True


What is the typical time horizon for aggregate planning?
A) less than a month
B) up to 3 months
C) 3 to 18 months
D) over one year

E) over 5 years - CORRECT ANSWER- ✔✔C

, Which of the following is the term used for intermediate-range capacity planning with a time
horizon of three to eighteen months?
A) material requirements planning
B) enterprise resource planning
C) strategic planning
D) aggregate planning

E) job scheduling - CORRECT ANSWER- ✔✔D


Which of the following is NOT one of the four things needed for aggregate planning?
A) a logical overall unit for measuring sales and output
B) a method to determine the relevant costs
C) a mathematical model that will minimize costs over the intermediate planning period
D) an aggregate demand forecast for an intermediate planning period

E) All of these are needed for aggregate planning. - CORRECT ANSWER- ✔✔C


What is the effort to plan the coordination of demand forecasts with functional areas of the
firm and its supply chain?
A) enterprise resource planning
B) material requirements planning
C) capacity planning
D) sales and operations planning

E) new product development - CORRECT ANSWER- ✔✔D


Which of the following is NOT an input to S&OP?
A) capacity decisions
B) supply-chain support
C) workforce
D) inventory on hand

E) master production schedule - CORRECT ANSWER- ✔✔E
€9,29
Accéder à l'intégralité du document:

Garantie de satisfaction à 100%
Disponible immédiatement après paiement
En ligne et en PDF
Tu n'es attaché à rien


Document également disponible en groupe

Faites connaissance avec le vendeur

Seller avatar
Les scores de réputation sont basés sur le nombre de documents qu'un vendeur a vendus contre paiement ainsi que sur les avis qu'il a reçu pour ces documents. Il y a trois niveaux: Bronze, Argent et Or. Plus la réputation est bonne, plus vous pouvez faire confiance sur la qualité du travail des vendeurs.
MGRADES Stanford University
S'abonner Vous devez être connecté afin de suivre les étudiants ou les cours
Vendu
1099
Membre depuis
1 année
Nombre de followers
102
Documents
68972
Dernière vente
6 heures de cela
MGRADES (Stanford Top Brains)

Welcome to MGRADES Exams, practices and Study materials Just think of me as the plug you will refer to your friends Me and my team will always make sure you get the best value from the exams markets. I offer the best study and exam materials for a wide range of courses and units. Make your study sessions more efficient and effective. Dive in and discover all you need to excel in your academic journey!

3,8

176 revues

5
75
4
31
3
47
2
8
1
15

Récemment consulté par vous

Pourquoi les étudiants choisissent Stuvia

Créé par d'autres étudiants, vérifié par les avis

Une qualité sur laquelle compter : rédigé par des étudiants qui ont réussi et évalué par d'autres qui ont utilisé ce document.

Le document ne convient pas ? Choisis un autre document

Aucun souci ! Tu peux sélectionner directement un autre document qui correspond mieux à ce que tu cherches.

Paye comme tu veux, apprends aussitôt

Aucun abonnement, aucun engagement. Paye selon tes habitudes par carte de crédit et télécharge ton document PDF instantanément.

Student with book image

“Acheté, téléchargé et réussi. C'est aussi simple que ça.”

Alisha Student

Foire aux questions