PRM3701 ASSESSMENT 2 SEMESTER 2 2024 Below are ways the Work Breakdown Structure (WBS) helps in managing projects. Which way listed below is incorrect a. with cost and time estimates the WBS makes it possible to plan, schedule and budget the project. b. i

Note
-
Vendu
-
Pages
54
Grade
A+
Publié le
15-08-2024
Écrit en
2024/2025

PRM3701 ASSESSMENT 2 SEMESTER 2 2024 Below are ways the Work Breakdown Structure (WBS) helps in managing projects. Which way listed below is incorrect a. with cost and time estimates the WBS makes it possible to plan, schedule and budget the project. b. it provides management with information appropriate to each level. c. can be used to define communication channels. d. allows the project manager to establish the overall objective of the project. e. as it is developed, organizational units and individuals can be assigned responsibility of work packages

Montrer plus Lire moins
Établissement
Cours











Oups ! Impossible de charger votre document. Réessayez ou contactez le support.

École, étude et sujet

Établissement
Cours

Infos sur le Document

Publié le
15 août 2024
Nombre de pages
54
Écrit en
2024/2025
Type
Examen
Contient
Questions et réponses

Sujets

Aperçu du contenu

PASSMATE TUTORIALS



DISCLAIMER: THIS IS NOT AN OFFICIAL GUIDE FROM UNISA. THE REPORT IS NOT
PREPARED NOR APPROVED BY UNISA, RATHER REPRESENTS A POSSIBLE
SOLUTION TO THE TASK CONSISTENT WITH THEORY. THIS ASSIGNMENT IS
INTENDED TO ASSIST STUDENTS IN GETTING STARTED WITH THEIR ASSIGNMENT,
AND IN NO CASE THIS DOCUMENT SHOULD BE USED FOR CHEATING. WE BELIEVE
THIS WILL BE A GOOD STARTING POINT AS IT WAS PREPARED BY OUR TEAM OF
PROFESSIONAL PRIVATE TUTORS WHO ARE EXPERTS IN THE FIELD, AND IT WAS
PREPARED USING VARIOUS SOURCES. ANY SIMILARITY WITH ANY EXISTING
THEORY OR DISCUSSION BY OTHER AUTHORS IS EXCUSED. THE AUTHORS
HOWEVER DO NOT CLAIM MONOPOLY TO KNOWLEDGE HENCE MODIFICATION OF
THE ANSWERS CONTAINED IN THIS FRAMEWORK MAY NOT BE PROHIBITED AS IT
CONTRIBUTES TO EXPANSION OF KNOWLEDGE. FOR ANY FURTHER GUIDELINE
ABOUT THE INFORMATION CONTAINED HERE AND THE MODULE IN GENERAL,
CONTACT PASSMATE TUTORIALS.

WE ASSIST WITH OTHER MODULES INCLUDING:

ECSs, FACs, MACs, MNGs, INTs, TRLs, HMEMS, PRMs, PROs, MNBs, DSC, QMI, MNMs,
MNO, MNPs, FIN, PUBs, MNMs, RESEARCH among others.

WE OFFER CLASSES, ASSIGNMENT GUIDELINES, EXAMINATION PREPARATION,
RESEARCH AND RESEARCH PROPOSALS, DISSERTATION EDITING etc.

OTHER THAN UNISA, WE ALSO ASSIST STUDENTS AT VARIOUS INSTITUTIONS
INCLUDING MANCOSA, REGENT, REGEYNESES, BOSTON, STADIO, OLG, UJ, UP etc

For any enquiries the following numbers can be used for calling, SMS, WhatsApp and
telegram

CONTACT PASSMATE TUTORIALS @061 262 1185/068 053 8213/0717 513 144




PLEASE READ THE NEXT PAGE!!!!!!!!!!!!!!!!




1
PASSMATE TUTORIALS 061 262 1185/068 053 8213/0717 513 144

, UNISA  2024  PRM3701-24-S2  Welcome Message  Assessment 2

QUIZ




Question 1

Not yet answered

Marked out of 1.00




You have just been given a project that has a specific completion date. After a
discussion with top management you find that while the date is important the
cost is more important and a slip in delivery would be acceptable if required to
meet the cost targets. The completion date is best classified as




a. constrained.

b. reduced.

c. accepted.

d. limited.

e. optional.

Clear my choice




Question 2
Not yet answered

Marked out of 1.00




Below are ways the Work Breakdown Structure (WBS) helps in managing
projects. Which way listed below is incorrect




a. with cost and time estimates the WBS makes it possible to plan,
schedule and budget the project.

b. it provides management with information appropriate to each level.

c. can be used to define communication channels.

d. allows the project manager to establish the overall objective of the
project.

e. as it is developed, organizational units and individuals can be assigned
responsibility of work packages.

Clear my choice

,Question 3

Not yet answered

Marked out of 1.00




The _________ is used to assist in making project trade-offs among schedule,
budget, and performance objectives.


a. responsibility matrix

b. responsibility matrix

c. project priority matrix

d. work package

e. criterion matrix

Clear my choice




Question 4
Answer saved

Marked out of 1.00




You are working for a marketing firm and has just been assigned manager of a
project to develop a new advertising campaign for an established product. What
is the second step the project manager should do?


a. Establish project priorities.

b. Define the project scope.

c. Verify the budget available.

d. Assign team members to work on the project.

e. Determine the required completion date.

Clear my choice




Question 5

Not yet answered

Marked out of 1.00




A home builder is collecting estimates for a house that he will have the funding
to build in 12 months. Which of the following factors does he need to consider
in regard to the quality of these estimates?


a. Padding estimates

b. Planning horizon

c. Project structure

d. People

e. Project duration

Clear my choice

, Question 6

Not yet answered

Marked out of 1.00




Which of the following is a good condition for top-down estimating?


a. Cost and time important

b. Fixed price contract

c. Customer wants details

d. Internal, small project

Clear my choice




Question 7
Not yet answered

Marked out of 1.00




Consider a five-mile-long railroad tunnel. Tunnel experts and advocates
estimate the total cost to be R200 million. What is the reference class for this
project? But reference class projects in this area have been over-budget by 30%.
So, what should the actual revised budget number be for this proposed five-mile
tunnel project?


a. Past bridge projects, R230 million

b. Past tunnel projects, R260 million

c. Past highway projects, R200 million

d. Past building projects, R230 million

e. Past construction projects, R230 million

Clear my choice




Question 8
Not yet answered

Marked out of 1.00




A purchasing agent is responsible for ordering hardware for a custom home his
company is building. The contractor installing the hardware is scheduled to
start in 5 working days, but the hardware is on backorder and will not arrive for
another 9 working days. Fortunately, the purchasing agent has 10 days of slack;
however, he shares this slack with the hardware installer. He will have to let the
contractor know that the hardware will be ready 4 days later than expected and
that the slack for the installer has been reduced by 4 days. The purchasing
agent and the installer share 10 days of


a. free slack.

b. shared slack.

c. total slack.

d. critical slack.

e. functional slack

Clear my choice
€3,95
Accéder à l'intégralité du document:

Garantie de satisfaction à 100%
Disponible immédiatement après paiement
En ligne et en PDF
Tu n'es attaché à rien


Document également disponible en groupe

Faites connaissance avec le vendeur

Seller avatar
Les scores de réputation sont basés sur le nombre de documents qu'un vendeur a vendus contre paiement ainsi que sur les avis qu'il a reçu pour ces documents. Il y a trois niveaux: Bronze, Argent et Or. Plus la réputation est bonne, plus vous pouvez faire confiance sur la qualité du travail des vendeurs.
passmatetutorials University of South Africa (Unisa)
S'abonner Vous devez être connecté afin de suivre les étudiants ou les cours
Vendu
1052
Membre depuis
2 année
Nombre de followers
695
Documents
673
Dernière vente
4 jours de cela
Passmate

We connect careers and dreams!

3,7

105 revues

5
50
4
13
3
21
2
5
1
16

Récemment consulté par vous

Pourquoi les étudiants choisissent Stuvia

Créé par d'autres étudiants, vérifié par les avis

Une qualité sur laquelle compter : rédigé par des étudiants qui ont réussi et évalué par d'autres qui ont utilisé ce document.

Le document ne convient pas ? Choisis un autre document

Aucun souci ! Tu peux sélectionner directement un autre document qui correspond mieux à ce que tu cherches.

Paye comme tu veux, apprends aussitôt

Aucun abonnement, aucun engagement. Paye selon tes habitudes par carte de crédit et télécharge ton document PDF instantanément.

Student with book image

“Acheté, téléchargé et réussi. C'est aussi simple que ça.”

Alisha Student

Foire aux questions