SWPP certifications are signed by - ANSWER ✔ : An
officer of the project owner or an officer of the general
contractor.
TRUE OR FALSE: The document that must be completed
signed and submitted to the state to obtain authorization to
discharge is the NOT - ANSWER ✔ : False
The notice of termination can be filed when - ANSWER ✔
: All construction inside and outside of the building is
completed and the final stabilization has been verified as
complete
Operators on a construction site are the entity in charge
of plans and specifications and the entity who is -
ANSWER ✔ : Is in charge of daily activities
You should have a SWPPP for your construction site
because (3 reasons) - ANSWER ✔ : 1. Its documents
stormwater management
2. Demonstrates your intent to manage stormwater on
your site
3. It is required by law
, A well constructed SWPPP for your site should be -
ANSWER ✔ : Site specific
The NO must be submitted - ANSWER ✔ : Prior to you
commencing construction
One necessary component of a good SWPPP is -
ANSWER ✔ : A schedule of activities
Factors that may impact the SWPPP scheduling activities
include - ANSWER ✔ : Weather and climate
Pollutant sources on a construction site may include (3) -
ANSWER ✔ : 1. petroleum storage tanks
2. Masonry material
3. soil amendment
The following considerations may be incorporatedd into
SWPPP - ANSWER ✔ : Endangered species and
historical preservation
If you beileve BMP modifications are necessary onsite
you must, - ANSWER ✔ : Seek written approval of the
project SWPPP designer and project owner
The SWPPP will contain the following (3) - ANSWER ✔ :
1. Erosion and sediment control bet management
practices
2. A site specific sequence of construction activiites