100% Verified Answers |Actual Complete Exam |
Already Graded A+ (Just Released)
An element of the project scope statement is:
A. Acceptance criteria.
B. A stakeholder list.
C. A summary budget.
D. High-level risks. ✔Correct Answer-A
Reserves Analysis ✔Correct Answer-Risk management method of determining contingency or
management reserves for schedule
Which document describes the necessary information to determine if a project is worth the required
investment?
A. Cost baseline
B. Service level agreement
C. Memorandum of understanding
D. Business case ✔Correct Answer-D
Which input to the Plan Risk Management process provides information on high-level risks?
A. Project charter
B. Enterprise environmental factors
C. Stakeholder register
D. Organizational process assets ✔Correct Answer-A
Which item is an example of personnel assessment?
A. Resource calendar
B. Tight matrix
C. Team-building activity
D. Focus group ✔Correct Answer-D
Which input to the Manage Stakeholder Engagement process provides guidance on how
stakeholders can best be involved in a project?
A. Feedback analysis
B. Stakeholder analysis
C. Communication management plan
D. Stakeholder management plan ✔Correct Answer-D
Which input to the Identify Stakeholders process provides information about internal or external
parties related to the project?
A. Procurement documents
,B. Communications plan
C. Project charter
D. Stakeholder register ✔Correct Answer-C
The Identify Stakeholders process is found in which Process Group?
A. Initiating
B. Monitoring and Controlling
C. Planning
D. Executing ✔Correct Answer-A
An input to Develop Project Charter is a/an:
A. Business case.
B. Activity list.
C. Project management plan.
D. Cost forecast. ✔Correct Answer-A
Which Knowledge Area involves identifying the people, groups, or organizations that may be
impacted by or impact a project?
A. Project Risk Management
B. Project Human Resource Management
C. Project Scope Management
D. Project Stakeholder Management ✔Correct Answer-D
Which input to Collect Requirements is used to identify stakeholders who can provide information on
requirements?
A. Stakeholder register
B. Scope management plan
C. Stakeholder management plan
D. Project charter ✔Correct Answer-A
In which Knowledge Area is the project charter developed?
A. Project Cost Management
B. Project Scope Management
C. Project Time Management
D. Project Integration Management ✔Correct Answer-D
The ability to influence cost is greatest during which stages of the project?
A. Early
B. Middle
C. Late
D. Completion ✔Correct Answer-A
Which process involves developing an approximation of the monetary resources needed to complete
project activities?
,A. Estimate Costs
B. Control Costs
C. Determine Budget
D. Plan Cost Management ✔Correct Answer-A
Which tool or technique is used in the Develop Project Management Plan process?
A. Pareto diagram
B. Performance reporting
C. SWOT analysis
D. Expert judgment ✔Correct Answer-D
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:
A. Responses
B. Appetite
C. Tolerance
D. Attitude ✔Correct Answer-A
An output of the Manage Stakeholder Engagement process is:
A. change requests
B. enterprise environmental factors
C. the stakeholder management plan
D. the change log ✔Correct Answer-A
Which process numerically analyzes the effect of identified risks on overall project objectives?
A. Plan Risk Management
B. Plan Risk Responses
C. Perform Quantitative Risk Analysis
D. Perform Qualitative Risk Analysis ✔Correct Answer-C
Which Collect Requirements output links the product requirements to the deliverable that satisfy
them?
A. Requirements documentation
B. Requirements traceability matrix
C. Project management plan updates
D. Project documents updates ✔Correct Answer-B
A temporary endeavor that creates a unique product or service is called a:
A. Project
B. Plan
C. Program
D. Portfolio ✔Correct Answer-A
The process of prioritizing risks for further analysis or action is known as:
A. Plan Risk Management.
B. Plan Risk Responses.
, C. Perform Qualitative Risk Analysis.
D. Perform Quantitative Risk Analysis. ✔Correct Answer-C
Stakeholder satisfaction should be managed as a key project:
A. Benefit
B. Initiative
C. Objective
D. Process ✔Correct Answer-C
Which cost is associated with nonconformance?
A. Liabilities
B. Inspections
C. Training
D. Equipment ✔Correct Answer-A
Identify Risks is part of which Process Group?
A. Planning
B. Executing
C. Closing
D. Initiating ✔Correct Answer-A
The business needs, assumptions, and constraints and the understanding of the customers needs
and high-level requirements are documented in the:
A. Project management plan.
B. Project charter.
C. Work breakdown structure.
D. Stakeholder register. ✔Correct Answer-B
Which Process Group and Knowledge Area include the Sequence Activities process?
A. Executing Process Group and Project Time Management
B. Executing Process Group and Project Cost Management
C. Planning Process Group and Project Time Management
D. Planning Process Group and Project Cost Management ✔Correct Answer-C
In the Plan Stakeholder Management process, expert judgment is used to:
A. Provide information needed to plan appropriate ways to engage project stakeholders.
B. Ensure comprehensive identification and listing of new stakeholders.
C. Analyze the information needed to develop the project scope statement.
D. Decide the level of engagement of the stakeholders at each required stage. ✔Correct Answer-D
Power, urgency, and legitimacy are attributes of which stakeholder classification model?