As a matter of good business practice, how should the
interior designer respond to questions from a bidder on
contract documents?
A.Answer each bidder's questions as they are asked.
B.Inform each bidder to make their own assumptions and
note each in the "Qualifications" section of their bid
[tender].
C.Document the questions and your responses in writing
and distribute to all bidders.
,2|Page
D.Invite all bidders to a meeting to review all the questions
and answers. - ANSWER-C.Document the questions and
your responses in writing and distribute to all bidders.
What portion of a contract typically outlines the designer's
responsibilities to the client?
A.Scope of services
B.Project description
C.Terms and conditions
D.Compensation schedule - ANSWER-A.Scope of
services
Which of the following has the GREATEST impact on the
effectiveness of an HVAC system?
,3|Page
A.Rooftop chiller size
B.Wall insulation type
C.Window treatments
D.Occupancy load - ANSWER-D.Occupancy load
While conducting a site visit, an interior designer notices
that the wall color does not match the paint submittal. Who
is responsible for the cost of repainting?
A.Interior designer
B.Manufacturer's representative
C.General contractor
D.Painting subcontractor - ANSWER-D.Painting
subcontractor
, 4|Page
What is the MOST important criterion to consider in
selecting a specialized consultant to work as part of an
effective design team?
A.The consultant's professional qualifications
B.How the consultant will personally fit as part of the
design team
C.The consultant's past experience working on similar
projects
D.The consultant's current workload and schedule -
ANSWER-A.The consultant's professional qualifications
An interior designer has specified a specialty paint product
for a project. Past experience with this product reveals that
the sample submitted was fine, but the painters in the field