Exam) | Complete Questions and Correct
Answers | Graded A+ | Verified Answers |
Latest Version | Brand New Version!
What is a claim? - >>> CORRECT ANSWER a written demand or assertion by one of the
contracting parties seeking (i) payment of a specific sum of money, (ii) adjustment or
interpretation of contract terms, or (iii) other relief arising under or relating to the
contract.
When is written certification for a claim required? - >>> CORRECT ANSWER When a
claim exceeds $100,000, contractors must provide the following written certification
(FAR 33.207).
What are protests? - >>> CORRECT ANSWER they provide offerors with a tool to
challenge federal contract award decisions.
Which clause is related to Acquisition? - >>> CORRECT ANSWER 52.215 - Instructions
to Offerors - Competitive Acquistion
What is considered a contract action? - >>> CORRECT ANSWER Contract action means
any oral or written action that results in the purchase, rent, or lease of supplies or
equipment, services, or construction.
What is latent defect? - >>> CORRECT ANSWER is one that is not readily noticeable
upon reasonable inspection at the time of acceptance.
Who accepts the burden of latent defect? - >>> CORRECT ANSWER The burden is on
the government to prove that defective material and workmanship was the probable
cause of product failure or non-conformance.
Who can you submit a claim to? - >>> CORRECT ANSWER Contractor claims are
submitted to the KO
, Who do you file a protest with? - >>> CORRECT ANSWER The Government
Accountability Office
There is a janitorial contract for 2.8 million dollars for the entire base. What FAR part
would you use? - >>> CORRECT ANSWER Could be FAR Part 37 Service Contracting or
Far Part 12 Acquisition of Commercial Products and Commercial Services
What common form do you use for a modification? - >>> CORRECT ANSWER SF-30
What FAR Part is Acquisition Planning? - >>> CORRECT ANSWER FAR Part 7
What role does the Program Manager plan in Acquisition Planning? - >>> CORRECT
ANSWER The PM has overall responsibility of a contract
What is the KO's role in Acquisition Planning? - >>> CORRECT ANSWER Ensures plan is
implemented and developed.
What are the three phases of a life cycle? - >>> CORRECT ANSWER Pre-Award Phase
Award Phase
Post-award phase
What are the two parts of the Pre-award phase? - >>> CORRECT ANSWER Develop
Solicitation
Develop offer
Who develops a solicitation? - >>> CORRECT ANSWER The Government & The Buyer.
Who prepares an offer? - >>> CORRECT ANSWER The Contractor and the seller
During the post-award phase while the contract is being performed, who has
responsibility for quality? - >>> CORRECT ANSWER The Seller
What does the award phase involve? - >>> CORRECT ANSWER Involves all work
performed by the buyer and seller
The Post-award Phase is also known as - >>> CORRECT ANSWER Contract
Administration
What is the use of a procedure that is inconsistent with the FAR? - >>> CORRECT
ANSWER Deviation