100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4,6 TrustPilot
logo-home
Examen

P-99 Low Pressure Boiler COF FDNY Questions and Answers (100% Correct Answers) Already Graded A+

Puntuación
-
Vendido
-
Páginas
11
Grado
A+
Subido en
06-11-2025
Escrito en
2025/2026

P-99 Low Pressure Boiler COF FDNY Questions and Answers (100% Correct Answers) Already Graded A+

Institución
P-99 Low Pressure Boiler COF FDNY
Grado
P-99 Low Pressure Boiler COF FDNY









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
P-99 Low Pressure Boiler COF FDNY
Grado
P-99 Low Pressure Boiler COF FDNY

Información del documento

Subido en
6 de noviembre de 2025
Número de páginas
11
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

1
For Expert help and assignment solutions, +254707240657


P-99 Low Pressure Boiler COF FDNY
Questions and Answers (100% Correct
Answers) Already Graded A+
A fill line in an oil burner system is a line used to: [ ANS: ] Fill the
storage tank with oil.

The aquastat is located [ ANS: ] Below the water line.

All heating, combustion, and cooking equipment shall be installed
with adequate clearances from _______ construction. [ ANS: ]
© 2025 Assignment Expert




Combustible

The equipment must be provided with ______ or the building
construction shall be _____ _____. [ ANS: ] Insulation.
Guru01 - Stuvia




Fire Protected

During operation the surface of combustible construction
materials will not be raised to a temp higher than _____ degrees F.
[ ANS: ] 170 degrees

Equipment shall be so that the means of access for ordinary
operation and maintenance will not be _______. [ ANS: ]
Hazardous

Acceptance Tests:

Boilers shall not be placed in operation until they have been _____
and ____ and an equipment ____ _____ has been issued by the
______. [ ANS: ] Inspected and tested.

Use permit, commissioner

Periodic Inspections: All boilers must be inspected at least _____ a
_____ including chimney connections. [ ANS: ] Once a year

, 2
For Expert help and assignment solutions, +254707240657

Owners Annual Statement: The owner of each boiler shall file an
_____ written statement with the ________, specifying the _____of
each boiler and ______ for inspection. [ ANS: ] Annual,
commissioner, location, arrangement.

Field Tests: all piping and oil storage tanks shall be _______ tested
for tightness by the ______ before the system is operated. [ ANS: ]
Hydrostatically, contractor

The piping shall be tested at _____ times the max working pressure
applicable to that part of the piping system but at a pressure ____
than the test pressure required for the storage tank. [ ANS: ] 1/2,
© 2025 Assignment Expert




less

The min pressure for testing tanks shall be ____ times the max
working pressure but in no case less than ____ psi. [ ANS: ] 1 1/2, 25
psi
Guru01 - Stuvia




The hydrostatic pressure must be maintained until all ____ and
_____ have been visually inspected for ___, but in no case less than
_____ hour. [ ANS: ] Joints, connections, leaks, 1/2 hour.

A record must be kept of the pressure test showing the name of
the _____ and the _____ at which the piping and tank were tested.
[ ANS: ] Contractor, pressure

Gas piping must be tested by the _____ before operation. [ ANS: ]
Contractor

For oil burning systems, ____ ____ giving instructions for the care
and operation of the system shall be permanently located in an
easily _____ and _____ location near the equipment. [ ANS: ]
Instruction Cards, visible, accessible

No oil burning equipment shall be operated until an equipment
____ _____ has been issued by the commissioner, the requirements
of the ____ ____ control code have been met and until the
$13.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Guru01 Chamberlain College Nursing
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
230
Miembro desde
1 año
Número de seguidores
33
Documentos
21107
Última venta
18 horas hace

3.9

42 reseñas

5
21
4
8
3
7
2
1
1
5

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes