APM PFQ EXAM 2025 TEST BANK QUESTIONS
AND 100%VERIFIED ANSWERS (ALREADY
GRADED A+) ASSURED SUCCESS-LATEST
UPDATE
Which of the following is not a stage in an issue resolution process?
| | | | | | | | | | | |
a. Share the issue with stakeholders.
| | | |
b. Track the issue to closure. c. Escalate to the sponsor.
| | | | | | | | |
d. Apply change control. - CORRECT-ANSWER-A
| | | | |
Which of the following are challenges for a project manager developing
| | | | | | | | | |
and leading a project team?
| | | | |
1) Issues and incompatibility amongst team members
| | | | |
2) Getting the right skills and attributes amongst team members
| | | | | | | |
3) Co-location of team members in the same geographic area
| | | | | | | |
4) Lack of accountability of team members
| | | | |
a. 1, 2 & 3
| | |
,b. 1, 2 & 4
| | |
c. 1, 3 & 4
| | |
d. 2, 3 & 4 - CORRECT-ANSWER-C
| | | | |
Which of the following is an activity in a typical change control process?
| | | | | | | | | | | |
a. Recommendation.
b. Justification.
c. Planning.
d. Continuous improvement - CORRECT-ANSWER-A
| | |
The purpose of quality assurance is to:
| | | | | |
a. provide confidence the project will satisfy the relevant quality
| | | | | | | |
standards.
|
b. determine a set of procedures and standards for project
| | | | | | | |
management.
|
c. inspect, measure and test deliverables and processes.
| | | | | |
d. define the scope and specifics of a project's deliverables - CORRECT-
| | | | | | | | | |
ANSWER-A
|
,A project manager might use a PESTLE analysis in order to:
| | | | | | | | | |
a. mitigate all possible risks to the project.
| | | | | |
b. identify and mitigate factors that may affect the project.
| | | | | | | |
c. control technological change during the project.
| | | | |
d. consider team social roles in early stages of the project - CORRECT-
| | | | | | | | | | |
ANSWER-B
|
Which of the following are phases in an iterative project life cycle? 1)
| | | | | | | | | | | |
Concept 2) Feasibility 3) Deployment 4) Development
| | | | | |
a. 3 and 4 only
| | |
b. 1, 2 and 3| | |
c. 1 and 2 only
| | |
d. 2, 3 and 4 - CORRECT-ANSWER-D
| | | | |
Which of the following is the responsibility of a project manager?
| | | | | | | | | |
a. Ensuring a project is aligned to the organisation's strategy.
| | | | | | | |
b. Focusing on project benefits and aligning priorities.
| | | | | |
, c. Achieving the project's success criteria.
| | | |
d. Improving process, tools and techniques used in a project -
| | | | | | | | |
CORRECT-ANSWER-C
To develop and establish a proper communication plan within a project,
| | | | | | | | | |
the project manager needs to consider which type of analysis?
| | | | | | | | | |
a. Budget.
b. Stakeholder.
c. Resource.
d. Schedule - CORRECT-ANSWER-B | |
Which of the following is a responsibility of the project sponsor?
| | | | | | | | | |
a. Creating a project cost breakdown structure.
| | | | |
b. Authoring the project management plan.
| | | |
c. Creating a project work breakdown structure.
| | | | |
d. Owning the project business case. - CORRECT-ANSWER-D
| | | | | |
AND 100%VERIFIED ANSWERS (ALREADY
GRADED A+) ASSURED SUCCESS-LATEST
UPDATE
Which of the following is not a stage in an issue resolution process?
| | | | | | | | | | | |
a. Share the issue with stakeholders.
| | | |
b. Track the issue to closure. c. Escalate to the sponsor.
| | | | | | | | |
d. Apply change control. - CORRECT-ANSWER-A
| | | | |
Which of the following are challenges for a project manager developing
| | | | | | | | | |
and leading a project team?
| | | | |
1) Issues and incompatibility amongst team members
| | | | |
2) Getting the right skills and attributes amongst team members
| | | | | | | |
3) Co-location of team members in the same geographic area
| | | | | | | |
4) Lack of accountability of team members
| | | | |
a. 1, 2 & 3
| | |
,b. 1, 2 & 4
| | |
c. 1, 3 & 4
| | |
d. 2, 3 & 4 - CORRECT-ANSWER-C
| | | | |
Which of the following is an activity in a typical change control process?
| | | | | | | | | | | |
a. Recommendation.
b. Justification.
c. Planning.
d. Continuous improvement - CORRECT-ANSWER-A
| | |
The purpose of quality assurance is to:
| | | | | |
a. provide confidence the project will satisfy the relevant quality
| | | | | | | |
standards.
|
b. determine a set of procedures and standards for project
| | | | | | | |
management.
|
c. inspect, measure and test deliverables and processes.
| | | | | |
d. define the scope and specifics of a project's deliverables - CORRECT-
| | | | | | | | | |
ANSWER-A
|
,A project manager might use a PESTLE analysis in order to:
| | | | | | | | | |
a. mitigate all possible risks to the project.
| | | | | |
b. identify and mitigate factors that may affect the project.
| | | | | | | |
c. control technological change during the project.
| | | | |
d. consider team social roles in early stages of the project - CORRECT-
| | | | | | | | | | |
ANSWER-B
|
Which of the following are phases in an iterative project life cycle? 1)
| | | | | | | | | | | |
Concept 2) Feasibility 3) Deployment 4) Development
| | | | | |
a. 3 and 4 only
| | |
b. 1, 2 and 3| | |
c. 1 and 2 only
| | |
d. 2, 3 and 4 - CORRECT-ANSWER-D
| | | | |
Which of the following is the responsibility of a project manager?
| | | | | | | | | |
a. Ensuring a project is aligned to the organisation's strategy.
| | | | | | | |
b. Focusing on project benefits and aligning priorities.
| | | | | |
, c. Achieving the project's success criteria.
| | | |
d. Improving process, tools and techniques used in a project -
| | | | | | | | |
CORRECT-ANSWER-C
To develop and establish a proper communication plan within a project,
| | | | | | | | | |
the project manager needs to consider which type of analysis?
| | | | | | | | | |
a. Budget.
b. Stakeholder.
c. Resource.
d. Schedule - CORRECT-ANSWER-B | |
Which of the following is a responsibility of the project sponsor?
| | | | | | | | | |
a. Creating a project cost breakdown structure.
| | | | |
b. Authoring the project management plan.
| | | |
c. Creating a project work breakdown structure.
| | | | |
d. Owning the project business case. - CORRECT-ANSWER-D
| | | | | |