How is the EF computed?
A. Min{LS of all immediate following activities}
B. LF minus−Activity time
C. Max{EF of all immediate predecessors}
D. ES + Activity time - ANSWER-ES + Activity time
What is the most popular example of specialized software for
managing projects?
A. PERT/CPM+
B. Microsoft Project
C. Project Apple
D. Microsoft Management Tool - ANSWER-Microsoft Project
, Page |2
Which of the following is a limitation of PERT and CPM?
A. The graphical nature of a network delays comprehension of the
activity list's interrelationships.
B. There is the inherent danger of placing too much emphasis on
the critical path.
C. They are applicable to only a narrow variety of projects and
industries.
D. They can be used only to monitor schedules. - ANSWER-
There is the inherent danger of placing too much emphasis on the
critical path.
What is the shortest duration required to complete an activity?
A. pessimistic time
B. optimistic time
C. crash time
D. most likely time - ANSWER-crash time
, Page |3
The three phases involved in the management of large projects
are
A. planning, scheduling, and evaluating.
B. scheduling, designing, and operating.
C. scheduling, operating, and evaluating.
D. planning, scheduling, and controlling. - ANSWER-planning,
scheduling, and controlling.
The project organization may be LESS helpful when
A. the project cuts across organizational lines.
B. the job is familiar to the existing organization.
C. work tasks can be defined with a specific goal and deadline.
D. the work contains complex interrelated tasks requiring
specialized skills. - ANSWER-the job is familiar to the existing
organization.
Which of the following is NOT part of project controlling?
, Page |4
A. close monitoring of resources, costs, quality, and budgets
B. shifting resources to where they are needed most
C. sequencing and allotting time to all project activities
D. using a feedback loop to revise the project plan - ANSWER-
sequencing and allotting time to all project activities
Which of the following is used for computations in CPM?
A. pessimistic time
B. normal time
C. optimistic time
D. most likely time - ANSWER-normal time
Which of the following is an advantage of PERT and CPM?
A. Straightforward concept and not mathematically complex.
B. Useful in monitoring only schedules.