100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4.2 TrustPilot
logo-home
Examen

Test 2 Objective Assessment Complete frequently TESTED Exam Questions with Definitive Correct Answers A+ Graded!!100% Guaranteed Pass!!<<Latest Version>>

Puntuación
-
Vendido
-
Páginas
39
Grado
A+
Subido en
20-09-2025
Escrito en
2025/2026

Test 2 Objective Assessment Complete frequently TESTED Exam Questions with Definitive Correct Answers A+ Graded!!100% Guaranteed Pass!!&lt;&lt;Latest Version&gt;&gt; Calculate the minimum size of the branch circuit conductors to source a motor given the following conditions: Operating Voltage: 480 volts. Electric Power: Three Phase - Motor Horsepower: 40 HP - Nameplate Rating: 50 amperes - Duty-Cycle Service: 15 minute, Intermittent duty 1. 12 AWG. 2. 6 AWG. 3. 4 AWG. 4. 3 AWG. - ANSWER 2. 6 AWG According to the National Electrical Code, what would be the calculated minimum trade size equipment grounding conductor required to protect one 5 HP, 208 V, 3- phase motor? Consider all the exceptions for rating or setting for individual motor circuits, and the use of an instantaneous trip breaker. 1. 2 AWG 2. 3 AWG 3. 4 AWG 4. 6 AWG - ANSWER 4. 6 AWG A 15-minute rated, 115 V, 2 HP, 3 phase squirrel-cage motor is to be used for intermittent duty. The minimum allowable ampacity of the branch-circuit conductors serving the motor is 1. 11.6 amps 2. 13.6 amps 3. 16.0 amps 4. 20.4 amps - ANSWER 1. 11.6 amps Given. A circuit load draws a total of 48 amperes, the resistive load on the circuit is 5 Ohms, determine source voltage for this circuit. 1. 120 volts 2. 240 volts 3. 277 volts 4. 480 volts - ANSWER 2. 240 volts Using the optional method described in Article 220 of the NEC, what is the smallest feeder that can supply a multi-family building, given it has 60 units, with a 4,000 watt dryer in each unit? 1. 50 kW 2. 75 kW 3. 277 KW 4. 300 kW - ANSWER 2. 75 kw The minimum allowable radius of the inner edge of a bend in mineral insulated metal-sheathed cable is 1. 2-1/2 in. for a 1/2-in. cable 2. 6 in. for a 1-in. cable. 3. 7 in. for a 1-in. cable : 4. 7 in. for a 1/2-in. cable. - ANSWER 1. 2-1/2 in. For a 1/2 - in cable A controller (contactor) has been installed to control an automatically started one horsepower motor with a marked service factor of 1.15. The motor nameplate fullload current rating is 8.8 amperes. What is the maximum size overload device that may be installed in this controller? 1. 10.1 amperes 2. 11.0 amperes 3. 11.8 amperes 4. 12.3 amperes - ANSWER 2. 11.0 amperes What would be the minimum required branch circuit for a combined equipment load of the following? - One, 7,000 watt range top - One, 8,000 watt wall-mounted oven 1. 8 kW 2. 15 kW 3. 12 kW 4. 9.2 kW - ANSWER 4. 9.2 kw Given an office building plan that consists of 25,000 sq-ft, with no receptacles displayed on the plan. Calculate the demand load of the receptacles. 1. 22.5 kW 2. 23.25 kW 3. 25.0 kW 4. 28.5 kW - ANSWER 3. 25.0 kw A fixed storage-type water heater that has a capacity of 120 gal or less shall be considered a continuous load for the purposes of sizing branch circuits. Therefore, if the heater has an element with a nameplate. rating of 6kW at 240-vac singlephase, what would be the minimum fuse or breaker size to protect this circuit? 1. 40 2. 35 3. 30 4. 20. - ANSWER 2. 35

Mostrar más Leer menos
Institución
ATT 2
Grado
ATT 2











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
ATT 2
Grado
ATT 2

Información del documento

Subido en
20 de septiembre de 2025
Número de páginas
39
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

Test 2 Objective Assessment
Complete frequently TESTED Exam
Questions with Definitive Correct
Answers A+ Graded!!100%
Guaranteed Pass!!<<Latest
Version>>
Calculate the minimum size of the branch circuit conductors to source a motor
given the following

conditions: Operating Voltage: 480 volts.

Electric Power: Three Phase

- Motor Horsepower: 40 HP - Nameplate Rating: 50 amperes - Duty-Cycle
Service: 15 minute, Intermittent duty

1. 12 AWG.

2. 6 AWG.

3. 4 AWG.

4. 3 AWG. - ANSWER ✓ 2. 6 AWG

According to the National Electrical Code, what would be the calculated minimum
trade size equipment grounding conductor required to protect one 5 HP, 208 V, 3-
phase motor? Consider all the exceptions for rating or setting for individual motor
circuits, and the use of an instantaneous trip breaker.

1. 2 AWG

2. 3 AWG

3. 4 AWG

,4. 6 AWG - ANSWER ✓ 4. 6 AWG

A 15-minute rated, 115 V, 2 HP, 3 phase squirrel-cage motor is to be used for
intermittent duty. The

minimum allowable ampacity of the branch-circuit conductors serving the motor is

1. 11.6 amps

2. 13.6 amps

3. 16.0 amps

4. 20.4 amps - ANSWER ✓ 1. 11.6 amps

Given. A circuit load draws a total of 48 amperes, the resistive load on the circuit
is 5 Ohms, determine

source voltage for this circuit.

1. 120 volts

2. 240 volts

3. 277 volts

4. 480 volts - ANSWER ✓ 2. 240 volts

Using the optional method described in Article 220 of the NEC, what is the
smallest feeder that can supply a multi-family building, given it has 60 units, with
a 4,000 watt dryer in each unit?

1. 50 kW

2. 75 kW

3. 277 KW

,4. 300 kW - ANSWER ✓ 2. 75 kw

The minimum allowable radius of the inner edge of a bend in mineral insulated
metal-sheathed cable is

1. 2-1/2 in. for a 1/2-in. cable

2. 6 in. for a 1-in. cable.

3. 7 in. for a 1-in. cable :

4. 7 in. for a 1/2-in. cable. - ANSWER ✓ 1. 2-1/2 in. For a 1/2 - in cable

A controller (contactor) has been installed to control an automatically started one
horsepower motor with a marked service factor of 1.15. The motor nameplate full-
load current rating is 8.8 amperes. What is the maximum size overload device that
may be installed in this controller?

1. 10.1 amperes

2. 11.0 amperes

3. 11.8 amperes

4. 12.3 amperes - ANSWER ✓ 2. 11.0 amperes

What would be the minimum required branch circuit for a combined equipment
load of the following?

- One, 7,000 watt range top - One, 8,000 watt wall-mounted oven

1. 8 kW

2. 15 kW

3. 12 kW

4. 9.2 kW - ANSWER ✓ 4. 9.2 kw

, Given an office building plan that consists of 25,000 sq-ft, with no receptacles
displayed on the plan.

Calculate the demand load of the receptacles.

1. 22.5 kW

2. 23.25 kW

3. 25.0 kW

4. 28.5 kW - ANSWER ✓ 3. 25.0 kw

A fixed storage-type water heater that has a capacity of 120 gal or less shall be
considered a continuous load for the purposes of sizing branch circuits. Therefore,
if the heater has an element with a nameplate. rating of 6kW at 240-vac single-
phase, what would be the minimum fuse or breaker size to protect this circuit?

1. 40

2. 35

3. 30

4. 20. - ANSWER ✓ 2. 35

What is the secondary current of a single phase, step-up transformer if the primary
voltage is 120 volts, the secondary voltage is 600 volts, and the primary current is
10 amperes? (Assume no transformer
impedance)

1. 2 amperes

2. 5 amperes

3. 10 amperes

4. 50 amperes - ANSWER ✓ 1. 2 amperes
$13.79
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
SmartscoreAaron Chicago State University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
36
Miembro desde
1 año
Número de seguidores
3
Documentos
3023
Última venta
6 días hace
SMARTSCORES LIBRARY

Get top-tier academic support for Psychology, Nursing, Business, Engineering, HRM, Math, and more. Our team of professional tutors delivers high-quality homework, quiz, and exam assistance—ensuring scholarly excellence and grade-boosting results. Trust our collaborative expertise to help you succeed in any course at U.S.A Institutions.

3.8

4 reseñas

5
2
4
1
3
0
2
0
1
1

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes