A locality VSMP authority need to encompass enforcement authority and a time table of civil
consequences for enforcement movements in its neighborhood ordinance. The maximum
penalty the authority can also problem is - ANS-$32,500 in keeping with violation per day
A locality VSMP should be at least as stringent as what kingdom permit? - ANS-Construction
GP
A simple rooftop disconnect isn't recommended for residential masses less than - ANS-6,000
feet^2
A violation of the development gp is a contravention of the - ANS-stormwater management
act
Accumulated sediment must be eliminated from the sediment forebay each - ANS-three to 5
years or whilst 6 to 12" have amassed
Adverse weather causing a scheduled inspection to be risky can postpone an inspection with
the aid of ____ - ANS-one enterprise day, BUT this ought to be cited inside the SWPPP
Any civil penalty assessed by a court as a result of a summons issued via a locality VSMP
authority ought to be paid - ANS-into the locality's treasury
Any man or woman who violates..... Will be situation to a civil penalty not to exceed -
ANS-$32, 500
Are assist sports covered below the Construction GP? - ANS-Yes, if it meets precise
standards
At a minimal, a stormwater control facility shall be inspected with the aid of the accountable
kingdom agency on an - ANS-annual basis and after any typhoon that causes the capacity of
the ability's important spillway to be handed
Can vegetated emergency spillways be built into fill? - ANS-No, needs to be armored if
constructed into fill
CBPA LDAs do not require - ANS-Construction GP, Pollution prevention Plan, Additional
manipulate measures to address TMDL
CBPA LDAs should have - ANS-accredited E&SC plan, authorized SWM plan, neighborhood
approval to begin land disturbance, long-term maintenance agreement, production report
drawings
, Changes within the SWPPP should be made in a __ day period - ANS-7
Chesapeake Bay Preservation Areas that result in a land disturbance more than or same to
____ and less than ____ - ANS-2,500 feet^2, 1 acre
Compliance necessities for channel safety rely on - ANS-type of channel being discharged to
and kind of flow
Concrete Wash Water must be directed into a - ANS-leak-proof field or leak-proof settling
basin
Corrective moves made based on inspections must be accomplished - ANS-as quickly as
viable but no later than seven days, or a longer time period as authorised by the VSMP
Date for the end of the economic year - ANS-October 1
DEQ has ___ days to finish evaluate of actual or capability inter-jurisdictional impacts upon
request - ANS-ninety
DEQ is needed to behavior a application evaluation once every - ANS-five years
DEQ is responsible for implementing the ____ even as locality ____ are accountable for
imposing local ordinances - ANS-Construction GP, VSMP
Difference among large and intensive for vegetated roof - ANS-extensive: low flora with
three" to six" boom medium, extensive medium 6 to 12"
Difference among degree 1 and stage 2 filtering practices - ANS-level 1 is a one cellular
design and level 2 is a two mobile layout
Difference among degree 1 and level 2 permeable pavement - ANS-for level 1, UD is
required
Difference among raise sizes for standard earthen embankment and component around pipe
- ANS-lift sizes for fashionable are 8", around the pipe are 4"
Difference in swale slopes for wet swale stage 1 and degree 2 - ANS-stage 1 swale slopes
much less than 2%, level 2 swale slopes much less than 1%
Dimensions of a soil compost amended filter out - ANS-20 feet lengthy and 10 ft wide
Does the SWM plan address runoff at some point of or after production? -
ANS-submit-production
Erosion and sediment control measures ought to be used whilst the soil compost amended
vicinity is what size? - ANS-2,500 toes^2 or greater