When calibrating to check the high side of the rolling straight edge:
Place shims under the outer wheels
Place shims under the center wheel
Place the rolling straight edge on a surface that looks flat
Place a 3/16 inch shin under the center wheel. The gauge should read zero on both sides of the
gauge. - CORRECT ANSWERS Place a 3/16 inch shim under the center wheel. The gauge
should read zero on both sides of the gauge.
What do you need to know when manually checking the cross slope?
The level length
The lane width
Height from the end of the level to pavement surface
The diameter of the bubble in the level - CORRECT ANSWERS Level length and height
from the end of level to pavement surface
When paving 5 foot wide shoulders or open-graded friction course FC-5 cores should be taken
at the frequency of...
1 per 100 feet
5 per lot
5 per sub lot
1 per 1000 feet
None of the above - CORRECT ANSWERS None of the above
Density cores for acceptance testing are not required for:
Mix less than 1 inch thick
Shoulders less than 5 feet wide
, ASPHALT PAVING LEVEL 1 QUESTIONS AND ANSWERS UPDATED
2025/2026 A COMPLETE EXAM SOLUTION ALL ANSWERS 100%
CORRECT VERIFIED BEST RATED A+ FOR SUCCESS
Acceleration and deceleration lanes less than 1000 feet in length
Ramos less than 1000 feet - CORRECT ANSWERS All of the above
If a core sample is needed just after paving then
Coring can be done immediately
Let the pavement be cool to the touch before coring
Run extra water from the core rig while coring
Wait until the pavement surface temperature has cooled below 160 degrees before coring -
CORRECT ANSWERS Wait until the pavement surface temp has cooled below 160
degrees before coring
Align the core barrel over the marked sampling location so that
It is a slight angle to the pavement
It is perpendicular to the truck bumper
It is perpendicular to the pavement surface
The top of the barrel is tilted slightly towards the truck - CORRECT ANSWERS It is
perpendicular to the pavement surface
How should asphalt cores be stored when transporting in hot weather?
Stacked on top of each other in a box for each project being sampled
By standing them upright in a cool shady location
By lying them flat in the back of a truck
In the cab of a un air conditioned truck - CORRECT ANSWERS By standing them upright
in a cool shady location
Asphalt placed when the mix temperature is too low can cause which of the following
problems?
2025/2026 A COMPLETE EXAM SOLUTION ALL ANSWERS 100%
CORRECT VERIFIED BEST RATED A+ FOR SUCCESS
When calibrating to check the high side of the rolling straight edge:
Place shims under the outer wheels
Place shims under the center wheel
Place the rolling straight edge on a surface that looks flat
Place a 3/16 inch shin under the center wheel. The gauge should read zero on both sides of the
gauge. - CORRECT ANSWERS Place a 3/16 inch shim under the center wheel. The gauge
should read zero on both sides of the gauge.
What do you need to know when manually checking the cross slope?
The level length
The lane width
Height from the end of the level to pavement surface
The diameter of the bubble in the level - CORRECT ANSWERS Level length and height
from the end of level to pavement surface
When paving 5 foot wide shoulders or open-graded friction course FC-5 cores should be taken
at the frequency of...
1 per 100 feet
5 per lot
5 per sub lot
1 per 1000 feet
None of the above - CORRECT ANSWERS None of the above
Density cores for acceptance testing are not required for:
Mix less than 1 inch thick
Shoulders less than 5 feet wide
, ASPHALT PAVING LEVEL 1 QUESTIONS AND ANSWERS UPDATED
2025/2026 A COMPLETE EXAM SOLUTION ALL ANSWERS 100%
CORRECT VERIFIED BEST RATED A+ FOR SUCCESS
Acceleration and deceleration lanes less than 1000 feet in length
Ramos less than 1000 feet - CORRECT ANSWERS All of the above
If a core sample is needed just after paving then
Coring can be done immediately
Let the pavement be cool to the touch before coring
Run extra water from the core rig while coring
Wait until the pavement surface temperature has cooled below 160 degrees before coring -
CORRECT ANSWERS Wait until the pavement surface temp has cooled below 160
degrees before coring
Align the core barrel over the marked sampling location so that
It is a slight angle to the pavement
It is perpendicular to the truck bumper
It is perpendicular to the pavement surface
The top of the barrel is tilted slightly towards the truck - CORRECT ANSWERS It is
perpendicular to the pavement surface
How should asphalt cores be stored when transporting in hot weather?
Stacked on top of each other in a box for each project being sampled
By standing them upright in a cool shady location
By lying them flat in the back of a truck
In the cab of a un air conditioned truck - CORRECT ANSWERS By standing them upright
in a cool shady location
Asphalt placed when the mix temperature is too low can cause which of the following
problems?