What is a general requirement of the location of the installation of a boiler? -
(ANSWER)Adequate clearance from combustile construction
What temperature must the materials remain under during combustion? - (ANSWER)170
degrees
What is a requirement for the access of the boiler? - (ANSWER)Access for operation and
maintenance must not be hazardous
What is required upon installation to operate a boiler? - (ANSWER)Inspection and test resulting
in equipment use permit from commissioner
How often should a boiler be inspected? - (ANSWER)Once a year
What documentation is required from a certificate holder? - (ANSWER)Owners annual
statement
, 2|Page
What is required to hydrostatically test upon installation and who should perform these tests? -
(ANSWER)Liquid fuel piping and fuel oil storage tanks by the installing contractor
At what pressure should piping be tested? - (ANSWER)1/2 max working pressure but less than
pressure required for storage tank
At what pressure should oil storage tanks be tested? - (ANSWER)At 1 1/2x max working
pressure but never < 25 psi
How long should hydrostatic pressure be maintained? - (ANSWER)Until all joints and
connections are inspected for leaks and at 30 minutes have passed
Who is responsible for testing gas distribution piping? - (ANSWER)Installing contractor before
closing and operation
What is described on instruction cards and where are they located? - (ANSWER)Care and
operation of oil burner located near the equipment.
What type of burners require a C of F holder to operate them? - (ANSWER)Any boiler that is not