100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4.2 TrustPilot
logo-home
Examen

ICC CALIFORNIA UST SERVICE TECHNICIAN LATEST UPDATED 2025/2026 EXAM REAL EXAM 250+ COMPLETE QUESTIONS AND SURE VERIFIED ANSWERS 100% GRADED AT A+ SCORE SURE GUARANTEED PASS!!

Puntuación
-
Vendido
-
Páginas
139
Grado
A+
Subido en
04-04-2025
Escrito en
2024/2025

ICC CALIFORNIA UST SERVICE TECHNICIAN LATEST UPDATED 2025/2026 EXAM REAL EXAM 250+ COMPLETE QUESTIONS AND SURE VERIFIED ANSWERS 100% GRADED AT A+ SCORE SURE GUARANTEED PASS!! Which agency approves a site-specific variance which allows for an alternative method of construction or monitoring: a.) The Regional Water Quality Board b.) The State Water Resources Control Board c.) The Department of Toxic Substance Control d.) The local agency - ANSWER a.) The Regional Water Quality Board CCR Title 23, Sec 2681(a) 2. Which of the following is not a confined space: a.) A really deep turbine sump b.) A space not designed for continuous employee occupancy c.) An area with limited access d.) An area with limited ventilation - ANSWER d.) An area with limited ventilation CCR Title 8, Sec 5157(b) 3. The regulations to enforce compliance of underground storage tank systems in the state are found in? a.) Code of Federal Regulations, 40 CFR Part 281 b.) California Code of Regulations, Title 23, Chapter 16 c.) Code of Federal Regulations, 40 CFR Part 280 d.) California Code of Regulations, Title 23, Chapter 17 - ANSWER b.) California Code of Regulations; Title 23, Chapter 16 4. A secondary containment system which is not an t ofintegral par primary containment shall be designed and constructed according to an engineering specification approved by a third party. The secondary containment system shall contain ______________ of the volume of the largest primary container within it, in the case of multiple primary containers: a.) 100 percent b.) 10 percent c.) 110 percent d.) 150 percent - ANSWER d.) 150 percent CCR Title 23, Sec 2631(e)(1)(B) 5. By definition an "underground storage tank system" includes a.) The tank, all connected piping and dispensers b.) The tank, all connected piping, ancillary equipment and containment system c.) Only the tank d.) Only tanks totally beneath the surface of the ground - ANSWER b.) The tank, all connected piping, ancillary equipment and containment system (H&SC, Sec 25281(z)) 6. The written report submitted to the local agency after an unauthorized release is required to include the following except: a.) Description of actions taken to stop the release b.) Cause of the release c.) Method of disposal of released product d.) Date on which the release was discovered - ANSWER b.) Cause of the release CCR Title 23, Sec 2652(c) 7. An unauthorized release which does not escape from secondary containment only requires a record on the operator's monitoring reports provided: A. It did not increase the hazard of fire B. It did not cause any deterioration of the secondary containment C. It was cleaned up within 8 hours of detection D. All of the above - ANSWER D. All of the above H&SC, Sec 25294 8. The annual monitoring certification may be performed by: A. A person possessing the appropriate contractors licenses B. An individual trained and certified by the manufacturer of the monitoring equipment C. A designated UST operator D. A person who meets the requirements of both a and b - ANS

Mostrar más Leer menos
Institución
ICC CALIFORNIA UST SERVICE TECHNICIAN
Grado
ICC CALIFORNIA UST SERVICE TECHNICIAN











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
ICC CALIFORNIA UST SERVICE TECHNICIAN
Grado
ICC CALIFORNIA UST SERVICE TECHNICIAN

Información del documento

Subido en
4 de abril de 2025
Número de páginas
139
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

ICC CALIFORNIA UST SERVICE TECHNICIAN
LATEST UPDATED 2025/2026 EXAM
REAL EXAM 250+ COMPLETE QUESTIONS
AND SURE VERIFIED ANSWERS 100%
GRADED AT A+ SCORE SURE
GUARANTEED PASS!!

1. Which agency approves a site-specific variance which allows for an
alternative method of construction or monitoring:
a.) The Regional Water Quality Board
b.) The State Water Resources Control Board
c.) The Department of Toxic Substance Control
d.) The local agency - ANSWER ✔ a.) The Regional Water Quality
Board
CCR Title 23, Sec 2681(a)

2. Which of the following is not a confined space:
a.) A really deep turbine sump
b.) A space not designed for continuous employee occupancy
c.) An area with limited access
d.) An area with limited ventilation - ANSWER ✔ d.) An area with
limited ventilation
CCR Title 8, Sec 5157(b)


3. The regulations to enforce compliance of underground storage tank
systems in the state are found in?
a.) Code of Federal Regulations, 40 CFR Part 281
b.) California Code of Regulations, Title 23, Chapter 16

,c.) Code of Federal Regulations, 40 CFR Part 280
d.) California Code of Regulations, Title 23, Chapter 17 - ANSWER ✔
b.) California Code of Regulations; Title 23, Chapter 16



4. A secondary containment system which is not an integral part of
primary containment shall be designed and constructed according to an
engineering specification approved by a third party. The secondary
containment system shall contain ______________ of the volume of the
largest primary container within it, in the case of multiple primary
containers:
a.) 100 percent
b.) 10 percent
c.) 110 percent
d.) 150 percent - ANSWER ✔ d.) 150 percent
CCR Title 23, Sec 2631(e)(1)(B)


5. By definition an "underground storage tank system" includes
a.) The tank, all connected piping and dispensers
b.) The tank, all connected piping, ancillary equipment and containment
system
c.) Only the tank
d.) Only tanks totally beneath the surface of the ground - ANSWER ✔
b.) The tank, all connected piping, ancillary equipment and containment
system

(H&SC, Sec 25281(z))

6. The written report submitted to the local agency after an unauthorized
release is required to include the following except:
a.) Description of actions taken to stop the release
b.) Cause of the release

,c.) Method of disposal of released product
d.) Date on which the release was discovered - ANSWER ✔ b.) Cause
of the release
CCR Title 23, Sec 2652(c)

7. An unauthorized release which does not escape from secondary
containment only requires a record on the operator's monitoring reports
provided:
A. It did not increase the hazard of fire
B. It did not cause any deterioration of the secondary containment
C. It was cleaned up within 8 hours of detection
D. All of the above - ANSWER ✔ D. All of the above
H&SC, Sec 25294

8. The annual monitoring certification may be performed by:
A. A person possessing the appropriate contractors licenses
B. An individual trained and certified by the manufacturer of the
monitoring equipment
C. A designated UST operator
D. A person who meets the requirements of both a and b - ANSWER ✔
D. A person who meets the requirements of both a and b
CCR Title 23, Sec 2715(i)

9. When an automatic tank gauge is utilized for single-walled tank leak
detection, it shall generate a post-test hard copy data report of the
following information, except:
a.) Liquid volume
b.) Fuel depth
c.) Outside air temperature
d.) Time and date of test - ANSWER ✔ c.) Outside air temperature
CCR Title 23, Sec 2643(b)(1)

, 10. If a UST system is utilizing an overfill alarm, the alarm must be
triggered to alert the transfer operator when the tank is no more than
___________ full
a.) 85%
b.) 95%
c.) 90%
d.) 80% - ANSWER ✔ c.) 90%

11. An automatic tank gauge is utilized for leak detection of the
______________.
a.) Tank
b.) Tank and Piping
c.) Piping
d.) Interstitial space - ANSWER ✔ a.) Tank
CCR Title 23, Sec 2643(b)(1)

12. After completion of enhanced leak detection (ELD) test, the ELD
test results must be submitted to the _________________.
a.) The local agency
b.) The SWRCB
c.) Owner of the UST system
d.) To both the SWRCB and the local agency - ANSWER ✔ d.) To both
the SWRCB and the local agency
CCR Title 23, Sec 2644.1(a)(5)

13. A permit to operate a UST system must have all of the following
listed on the permit, EXCEPT:
a.) The state UST identification number(s)
b.) Name of the tank manufacturer and tank capacity
c.) Permit expiration date
d.) Monitoring requirements - ANSWER ✔ b.) Name of the tank
manufacturer and tank capacity
CCR Title 23, Sec 2712(c)
$13.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Exchequer Teachme2-tutor
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
59
Miembro desde
11 meses
Número de seguidores
1
Documentos
1440
Última venta
1 semana hace
EXEMPLARY SERVICE IN ACADEMIA EXCELLENCY IN ACCADEMIC MATERIALS ie exams, study guides, testbanks ,case, case study etc

Assignments, Case Studies, Research, Essay writing service, Questions and Answers, Discussions etc. for students who want to see results twice as fast. I CAN DO ASSIGNMENTS, EXAMS,ESSAYS AND RESEARCH PROJECTS FOR YOU EVEN AT STRICT DEADLINES. I have done papers of various topics and complexities. I am punctual and always submit work on-deadline. I write engaging and informative content on all subjects. Send me your research papers, case studies, psychology papers, etc, and I’ll do them to the best of my abilities. Writing is my passion when it comes to academic work. I’ve got a good sense of structure and enjoy finding interesting ways to deliver information in any given paper. I love impressing clients with my work, and I am very punctual about deadlines. Send me your assignment and I’ll take it to the next level. I strive for my content to be of the highest quality. Your wishes come first— send me your requirements and I’ll make a piece of work with fresh ideas, consistent structure, and following the academic formatting rules. For every student you refer to me with an order that is completed and paid transparently, I will do one assignment for you, FREE of any fee.

Lee mas Leer menos
2.8

8 reseñas

5
3
4
0
3
1
2
0
1
4

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes