DBIA: Principles of Design-Build and Post Award & Contracts, Project Delivery Exam Questions and Answers Allows all federal agencies to utilize Design-Build. Prior to that no enabling legislation existed allowing Design-Build. What Year? - ANSWER-Clinger Cohen Act/Defense Procurement Reform Act 1996 The level of quality that any average Design Professional would be able to perform given the circumstances. - ANSWER-Standard of Care Fastest Project Delivery method, fast tracking possible overlapping design with construction utilizing incremental packages. - ANSWER-Design Build Procurement Method - Common for A/E - ANSWER-Negotiated (Qualifications Based) Contract Format - Combines Cost-Plus & Lump-Sum, contractor reimbursed for actual cost plus a fee only up to a certain amount. - ANSWER-GMP (Guaranteed Maximum Price) Contract Format - cost per piece - ANSWER-Unit Price Successful Design Build requires _____ & _______ between participants - ANSWER-Trust, Flexibility ©EMILLECT 2024/2025 ACADEMIC YEAR. ALL RIGHTS RESERVED FIRST PUBLISH OCTOBER 2024 Page 2/18 Singular responsibility for both design & construction was first made into a building code by ____ - ANSWER-Hammurabi Owner provided items such as 20% design or more and provides prescriptive specs at RFP. - ANSWER-Bridging Documents Single point of responsibility for both design & construction is an attribute of what delivery method? - ANSWER-Design Build The process of checking milestones along the way for completeness. - ANSWER-Substantiation Owner requiring specific products or methods be instituted by DB team in order to achieve desired performance. - ANSWER-Prescriptive T/F Detailed estimating is the Building systems approach to estimating - ANSWER-False T/F feasibility estimate is cost model and establishes budget for project - ANSWER-False T/F key element of quality assurance is keeping communication lines open between owner and DB - ANSWER-True T/F in Design/cost relationship of DB, the constructor establishes design parameters for architect - ANSWER-True T/F trust is most important thing for DB - ANSWER-False ©EMILLECT 2024/2025 ACADEMIC YEAR. ALL RIGHTS RESERVED FIRST PUBLISH OCTOBER 2024 Page 3/18 DB estimating sequence where 15%-20% of design is completed - ANSWER-Schematic estimating Provides baseline budgets and schedules and list estimate trends - ANSWER-Trend logs What is NOT a design managers role? - ANSWER-Coordinating owner design reviews and approvals Who is responsible for ensuring quality assurance? - ANSWER-Design Build Team Awarded to proposer with highest combined total points of technical and price proposals - ANSWER- Weighted criteria Estimate provided with very little design - ANSWER-Conceptual estimating Maintains control of budget and design process between major estimate phases - ANSWER-Trend estimating Owner proforma based on sq ft or ROM estimates - ANSWER-Feasibility

Mostrar más Leer menos
Institución
DBIA
Grado
DBIA










Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
DBIA
Grado
DBIA

Información del documento

Subido en
30 de octubre de 2024
Número de páginas
18
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

©EMILLECT 2024/2025 ACADEMIC YEAR. ALL RIGHTS RESERVED

FIRST PUBLISH OCTOBER 2024




DBIA: Principles of Design-Build and Post

Award & Contracts, Project Delivery Exam

Questions and Answers


Allows all federal agencies to utilize Design-Build. Prior to that no enabling legislation existed allowing

Design-Build. What Year? - ANSWER✔✔-Clinger Cohen Act/Defense Procurement Reform Act 1996


The level of quality that any average Design Professional would be able to perform given the

circumstances. - ANSWER✔✔-Standard of Care


Fastest Project Delivery method, fast tracking possible overlapping design with construction utilizing

incremental packages. - ANSWER✔✔-Design Build


Procurement Method - Common for A/E - ANSWER✔✔-Negotiated (Qualifications Based)


Contract Format - Combines Cost-Plus & Lump-Sum, contractor reimbursed for actual cost plus a fee only

up to a certain amount. - ANSWER✔✔-GMP (Guaranteed Maximum Price)


Contract Format - cost per piece - ANSWER✔✔-Unit Price


Successful Design Build requires _____ & _______ between participants - ANSWER✔✔-Trust, Flexibility


Page 1/18

, ©EMILLECT 2024/2025 ACADEMIC YEAR. ALL RIGHTS RESERVED

FIRST PUBLISH OCTOBER 2024




Singular responsibility for both design & construction was first made into a building code by ____ -

ANSWER✔✔-Hammurabi


Owner provided items such as 20% design or more and provides prescriptive specs at RFP. -

ANSWER✔✔-Bridging Documents


Single point of responsibility for both design & construction is an attribute of what delivery method? -

ANSWER✔✔-Design Build


The process of checking milestones along the way for completeness. - ANSWER✔✔-Substantiation


Owner requiring specific products or methods be instituted by DB team in order to achieve desired

performance. - ANSWER✔✔-Prescriptive


T/F Detailed estimating is the Building systems approach to estimating - ANSWER✔✔-False


T/F feasibility estimate is cost model and establishes budget for project - ANSWER✔✔-False


T/F key element of quality assurance is keeping communication lines open between owner and DB -

ANSWER✔✔-True


T/F in Design/cost relationship of DB, the constructor establishes design parameters for architect -

ANSWER✔✔-True


T/F trust is most important thing for DB - ANSWER✔✔-False


Page 2/18

, ©EMILLECT 2024/2025 ACADEMIC YEAR. ALL RIGHTS RESERVED

FIRST PUBLISH OCTOBER 2024




DB estimating sequence where 15%-20% of design is completed - ANSWER✔✔-Schematic estimating


Provides baseline budgets and schedules and list estimate trends - ANSWER✔✔-Trend logs


What is NOT a design managers role? - ANSWER✔✔-Coordinating owner design reviews and approvals


Who is responsible for ensuring quality assurance? - ANSWER✔✔-Design Build Team


Awarded to proposer with highest combined total points of technical and price proposals - ANSWER✔✔-

Weighted criteria


Estimate provided with very little design - ANSWER✔✔-Conceptual estimating


Maintains control of budget and design process between major estimate phases - ANSWER✔✔-Trend

estimating


Owner proforma based on sq ft or ROM estimates - ANSWER✔✔-Feasibility estimate


Determines if proposer is qualified for project with yes or no statement - ANSWER✔✔-Statement of

qualifications


Contract for Design-Build Consultant Services - ANSWER✔✔-DBIA 501


Standard Form of Preliminary Agreement Between Owner and Design-Builder - ANSWER✔✔-DBIA 520


Standard Form of Agreement Between Owner & Design-Builder for a Lump Sum - ANSWER✔✔-DBIA 525


Page 3/18
$11.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada


Documento también disponible en un lote

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Emillect West Virginia University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
28
Miembro desde
1 año
Número de seguidores
2
Documentos
3004
Última venta
2 meses hace
GOLDEN ORCHIDS STORE.

On this page, you find all documents, package deals, and flashcards offered by seller Emillect.

3.0

4 reseñas

5
1
4
0
3
2
2
0
1
1

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes