Supplemental Information
Exam Questions With Revised
Correct Detailed Answers
|ALREADY GRADED A+ PASS
>> BRAND NEW VERSION!
1) UST system records must be maintained on-site____;
a. without exception
b. or at a location approved by the State Water Resource Control Board
c. only during facility operating hours
d. or at a location approve the Local Agency - ANSWER d. or at a location
approve the Local Agency
2) A written statement indicating statistical inventory reconciliation results must
be submitted to the____every___;
a. Local Agency, 12 months
b. State Water Resource Control Board and the Local Agency, 36 months
c. State Water Resource Control Board and the Local Agency, 12 months
d. Local Agency, 36 months - ANSWER a. Local Agency, 12 months
,3) As of October 13, 2018, Emergency Generator Tank Systems must include
which of the following:
a. line leak detectors installed on pressurized piping
b. inventory reconciliation performed every 30 days
c. cathodic protection system must be installed
d. under dispenser containment - ANSWER a. line leak detectors installed on
pressurized piping
4) True or false? Buried single-walled pipe may be replaced with single-walled
pipe if the length is less than 50 feet
a. true
b. false - ANSWER b. false
5) Ball float valves may not be utilized to provide overfill prevention as of:
a. october 13, 2021
b. october 1, 2018
c. January 1, 2005
d. January 1, 2020 - ANSWER b. october 1, 2018
6) As of October 13, 2018, if an owner/operator plans to change the substance
stored in the tank, which of the following must be provided to the CUPA in writing
at least 30 days before the change:
a. the specific substance to be stored
b. the date the storage will commence
c. Documentation demonstrating compatibility
d. all of the above - ANSWER d. all of the above
,9) True or false? Late testing and inspections do not reset the next deadline
a. true
b. false - ANSWER a. true
10) As of October 13, 2018, how often must the overfill prevention equipment be
inspected?
a. every 30 days
b. annually
c. every 36 months
d. every 5 years - ANSWER c. every 36 months
11) How often must the Designated UST Operator Visual Inspection be performed
at the least?
a. monthly
b. every 30 days
c. quarterly
d. annually - ANSWER b. every 30 days
12) All of the following must be inspected as part of the Designated Operator
Visual Inspection, except:
a. inspect spill container and UDC for damage
b. inspect fill pipe for obstructions
c. check fuel sales for discrepancies
, d. verify the fill cap fits securely on the fill pipe - ANSWER c. check fuel sales
for discrepancies
13) How long must spill container testing and overfill inspection records must be
kept?
a. one year
b. 6 months
c. 36 months
d. 5 years - ANSWER c. 36 months
14) After the repair of a spill container or overfill protection equipment, how
much time do you have to retest the repaired equipment?
a. 30 days
b. 60 days
c. 6 months
d. 1 year - ANSWER a. 30 days
15) The UST Service Technician performing a spill container test or overfill
prevention inspection must (select all that apply):
a. have a least 5 years of experience
b. have performed at least 10 similar tests/inspections under the supervision of
another technician
c. be trained and/or certified by the manufacturer of the equipment, the
developer of the test method or equipment, or a comparable training and
certification method