VA Contractors: VA Advanced (Class A) exam 2024 with 100% correct answers
A lump sum contract on a project has a total contract price of $160,000. Retainage has been held back at 10%. The contractor has received progress payments for 75% of the project. The contractor submits a request for final payment for the new completed project. The final payment amount should be for... correct answersMore than $50,000 What is the total value of current assets for an accrual basis company that has the following? Checking account cash balance is $4,800; materials inventory for work-in-progress is $4,200; a pick-up truck that cost $12,460- paid for with $2,460 in cash and a note for $10,000- and is used 100% in the business; accounts receivable is $5,700; suppliers' accounts payable is $6,300; other accounts payable is $2,200; and quarterly income tax payment due is $1,180... correct answersBetween $12,000 and $16,000 What is the total project overhead for a project that lasts 3 months and has the following costs? Labor is $4,000; materials are $9,500; equipment rentals are $1,200; superintendent's annual salary is $36,000; office rent is $800 per month; and office utilities are $375 per month. correct answersLess than $12,000 For 1 month a company bills out $38,000 in completed work, and receives $22,000 in payments plus $8,000 from the previous month's billings. They pay their total bill of $26,000 to supply houses for this month's purchases, and another $5,000 to supply houses for last month's purchases. Using a cash accounting method and NOT considering any other revenue or expenses, what is the company's net income for the month? correct answersLoss of $1,000 The owner requests for change which will cost the contractor $15,000 in labor and materials and $2,250 in overhead costs. With the change, the contractor would be relieved of $18,000 in labor and materials costs, and $2,400 in overhead costs from the original contract. The original bid included profit of 20% of all costs. The contractor wants to make a profit of 20% of all costs on the changes. The adjusted contract price for the change order should be... correct answersA decrease of $3,780 Which of the following would typically be covered by a contractor's comprehensive general liability insurance policy? correct answersDamage to adjoining property from a crane accident
Escuela, estudio y materia
- Institución
- VA Contractors: VA Advanced
- Grado
- VA Contractors: VA Advanced
Información del documento
- Subido en
- 16 de mayo de 2024
- Número de páginas
- 4
- Escrito en
- 2023/2024
- Tipo
- Examen
- Contiene
- Preguntas y respuestas
Temas
-
va contractors va advanced class a