MNB2601 ASSESSMENT 1 SEMESTER 1 2024 SEARCHABLE In which of the following estimation methods is a probabilistic analysis applied to determine the properties of the estimated forecast? For estimation to be effective, a threshold level of confidence must

Puntuación
-
Vendido
1
Páginas
30
Grado
A+
Subido en
12-05-2024
Escrito en
2023/2024

MNB2601 ASSESSMENT 1 SEMESTER 1 2024 SEARCHABLE In which of the following estimation methods is a probabilistic analysis applied to determine the properties of the estimated forecast? For estimation to be effective, a threshold level of confidence must be set. The threshold level is usually decided at the start of a project. Which one of the following levels of rigour in the estimation process is generally accepted and has a variance of 10%? Which of the following statements concerning the precedence diagramming method (PDM), as a scheduling method, is incorrect? In managing estimates, variance analysis is performed, assuming that sound and reliable estimates were calculated to the expected level of confidence. In respect of which of the common causes of variance is a recommendation made to take care in developing and maintaining the basis of estimates?

Mostrar más Leer menos
Institución
Grado










Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Libro relacionado

Escuela, estudio y materia

Institución
Grado

Información del documento

Subido en
12 de mayo de 2024
Número de páginas
30
Escrito en
2023/2024
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

BMZ ACADEMY

BMZ Academy




CONTACT @ 061 262 1185/068 053 8213/0717513144




BMZ ACADEMY 0612621185/ 0717513144/ 068 053 8213

,5/12/24, 7:23 PM Assessment 4




MNB2601-24-S1  Welcome Message  Assessment 4

QUIZ




Time left 1:36:18

Question 1
Not yet answered

Marked out of 1.00




For estimation to be effective, a threshold level of confidence must be set. The threshold level is usually decided at the start
of a project.

Which one of the following levels of rigour in the estimation process is generally accepted and has a variance of 25%?


a. conceptual estimation



b. detailed estimation



c. definitive estimation



d. comprehensive estimation



Clear my choice




Question 2
Not yet answered

Marked out of 1.00




In which of the following estimation methods is a probabilistic analysis applied to determine the properties of the estimated
forecast?


a.
Monte Carlo simulation



b.
probabilistic estimation



c.
power series estimation



d.
three-point estimation



Clear my choice




https://mymodules.dtls.unisa.ac.za/mod/quiz/attempt.php?attempt=19084976&cmid=879516 1/7

, 5/12/24, 7:23 PM Assessment 4

Question 3

Not yet answered

Marked out of 1.00




In managing estimates, variance analysis is performed, assuming that sound and reliable estimates were calculated to the
expected level of confidence.

In respect of which of the common causes of variance is a recommendation made to take care in developing and maintaining
the basis of estimates?


a. estimation errors



b. operational issues



c. approved changes



d. ambiguous requirements



Clear my choice




Question 4
Not yet answered

Marked out of 1.00




Which of the following statements concerning the precedence diagramming method (PDM), as a scheduling method, is
incorrect?


a.
PDM does not include the ability to introduce varying constraints.

b.
The tasks are sequenced between the start and finish of the project.

c. All tasks, except the start and the finish, have one or more predecessors and successors: no task is left unattended.

d. Relationships between tasks are indicated by arrows.

Clear my choice




https://mymodules.dtls.unisa.ac.za/mod/quiz/attempt.php?attempt=19084976&cmid=879516 2/7
$3.07
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
BMZAcademy University of South Africa (Unisa)
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
1880
Miembro desde
3 año
Número de seguidores
696
Documentos
1178
Última venta
1 semana hace
BMZ

academic stuffs, classes, assignments, notes, portfolios, research, Economics, Quantitative, Financials, Strategy, Management & Administration etc

4.0

266 reseñas

5
137
4
49
3
49
2
13
1
18

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes