SWM ponds must be able to convey water safely up to
what level storm event? - Answers-must be able to safely
convey up to a 100 yr storm.
Define LDA - Answers-Land disturbing activity; any man-
made change to the land surface that potentially changes
its runoff characteristics; includes clearing, grading, and
excavation.
What size LDA must comply with stormwater management
regulation? in CPBA areas? - Answers-anything of 1 acre
or more, or 2500 ft^2 in CPBA areas; may be more
stringent locally.
what are some activities exempt from SWM regulations? -
Answers-mining, agriculture, sewer discharges, local
reclamation programs, routine maintenance of preexisting
operations, public emergency activity
, 2|Page
what term basically means a plea deal for stormwater
offenders? - Answers-consent order, which replaces
penalties with fines.
how long does VSMP authority have to review SWM plan?
- Answers-15 days to review and determine approval, and
notify applicant.
How often must a VSMP authority inspect an LDA? -
Answers-Periodically.
all SWPPP requirements may be met by - Answers-
incorporating other plans into reference, or by developing
missing elements.
What must the DEQ issue to an operator before an LDA? -
Answers-a construction GP
How soon after final grade of a site must vegetation be put
in place? - Answers-within 7 days.
What element is targeted by water quality criteria? -
Answers-Phosphorous, it indicates pollution by bonding
with other pollutants.