What criteria does vegetation need in order to be
considered established? -
ANSWER-the ground cover
must be:
1) uniform
2) mature enough to survive
3) able to inhibit erosion
What legal agreement allows VSMP inspectors to access
property for conducting post-construction BMP
inspections? -ANSWER-A long-term maintenance
agreement
,Who must sign and seal a construction record drawing,
and when must it be submitted to the VSMP authority? -
ANSWER-must be signed by a professional registered in
VA. Must be submitted before permit termination.
How much time does the VSMP authority have to
terminate any bonds or securities provided by the
operator? - ANSWER- Within 60 days of completing the
requirements of the permit conditions
, How often must a VSMP authority inspect a SWM facility
post- construction? - ANSWER-Every 5 years, OR the
owner may submit reports completed be a qualified person
on an annual basis
, What is the TP limit for a site? - ANSWER-0.41 lbs/ac/yr
The phosphorus load limit uses what % impervious cover?
-ANSWER-10%
Part II B and II C water quantity criteria addresses: -
ANSWER-channel protection and flood
protection
Of all the plans included in the SWPPP, which two must
be approved? -ANSWER-the SWM and ESC
Plans