AIC ACTUAL FINAL EXAM Complete 250 Questions And Correct Detailed Answers (Verified Answers) |Already Graded A+ LATEST UPDATE!! 1. A project schedule has been updated. The activity placement of spread footing concrete was originally scheduled to begin as early as day 10. The activity duration is 4 days. The actual start day was day 12. The original schedule had calculated total float of 7 days for this activity. The recalculated total float for the activity, when updated, would be... A. 2 days B. 5 days C. 6 days D. 9 days B. 5 Days 2. The purpose of retainage is to encourage the general contractor to? a. Submit payment request on time b. Complete project per contract c. Get construction materials on site quickly d. Staff all areas of the project in a timely fashion b. Complete project per contract 1/5/26, 9:40 PM AIC Exam 2/104 3. A 'place concrete' activity requires the placement of 2080 cubic yards. If the individual production rate is 2 cubic yards per work hour per person, with a 10- person crew and 8 hour workday, how many days are needed to complete this activity? a.13 b.26 c.104 d.130 a. 13 4. What method is used to calculate activity duration? a. Daily production rate divided by plan quantity b. Plan quantity divided by crew rate c. Plan quantity divided by daily production rate d. Plan quantity dived by labor unit cost c. plan quantity divided by daily perfromance 5. Which of the following can be identified from the initial schedule of values? a.Vendors working on the project b. Contractors proposed breakdown of the project cost c. Profit margin of the applicant d. Quality of work in place b. contractors proposed breakdown of the project cost 1/5/26, 9:40 PM AIC Exam 6. The architect has approved the rerouting of an HVAC through concrete slabs in a building. To insure that activities are coordinated, a meeting should be called by the field supervisor and the a. HVAC subcontractor only b. HVAC subcontractor and all other subcontractors c. HVAC subcontractor and all other affected subcontractors d. HVAC subcontractor and the architect engineer? c. HVAC subcontractor and all other affected subcontractors 3/104 1/5/26, 9:40 PM AIC Exam 4/104 7. Concrete to be poured for 10 footings are 5 feet wide by 5 feet long by 2 feet deep. How many cubic yards of concrete should the estimate be for this pour, using a 10% waste factor. a.14.8 b.16.3 c.18.5 d.20.3 d. 20.3 8. A topographical map is a drawing showing? a.Subsurface soil conditions b. A general profile view of the site c. Contour lines and elevations d. Cross sections along the length of the project. c. Contour lines and elevations 9. The location of reinforcing steel used in a concrete member should be placed where? a. Shear is minimal b. Concrete is in tension c. Concrete is in compression d. Center axis is located. b.Concrete is in tension 1/5/26, 9:40 PM AIC Exam 5/104 10. The owner's rep observed substandard drywall patches on a general contractor's renovation project. Which of the following should be the representative's first course of action? a. Save items for punch list b. Notify drywall finisher of the problem c. Tell painter not to accept patched walls d. Notify general contractors superintend of problem. d. Notify general contractors superintended of problem 11. A contract for a project contains a liquidated damages clause. The project is under compensable delay for 4 days. In addition, rain caused another 5-day non- compensable delay. How should the delay be handled? a. The contractor should assume the costs of the 5-day delay less the cost owed by the owner for the 4 day delay b. Since both delays have caused an explanation of the completion date, contractor should be liable to the owner for the costs for a total delay of 9 days c. The contractor should request a 5-day time extension due to the rain, and should be compensated for the 4 days compensable delay by the owner d. The costs delay is overridden by the delay due to the rain. The owner is relieved of compensable delay, and the contractor should assume the costs of 5 days delay c. The contractor should request a 5-day time extension due to the rain, and should be compensated for the 4 days compensable delay by the owner 1/5/26, 9:40 PM AIC Exam 6/104 12. Which of the following is required for an employee to operate a powder operated tool? a. Drivers licence b. Contract terms c. Completed training card d.Osha ten hour card c. Completed training card 13. A contingency fund would be used for? a.Unknown conditions b. Stipulated price increase c. Purchase of backup equipment d. Concrete quantities taken from the drawings a. Unknown conditions 14. The uniform construction code is an area of a.Material suppliers b. Subcontractor services c. Federal subcontractors d. Contract in excess of 1 million dollars a. Material Suppliers 1/5/26, 9:40 PM AIC Exam 7/104 15. Assume the elevated slab is designed for 100 psf. The pipe subcontractor requests permission of the site superintend to use a mobile scissor lift on a elevated slab. The lift has a contact area of 30"X60". It weighs 1,100 lbs and has a load capacity of 500 lbs. what action should the site superintendent take? a. Allow use of the lift b. Deny use of the lift c. Refer the problem to the architect d. Refer the problem to the designer of the lift a. Allow use of the lift 16. The baseline schedule or target should be maintained in order to analyse the? a. Variance in progress of the project b. Float time is the current schedule c. Critical path d. Correlative effect of the "leach" a. Variance in progress of the project 17. A project bid comes in over budget. The architect might request proposal from some, or all of the bidders to suggest ways to reduce costs without degrading the quality of the project. What term describes this accurately? a. Value engineering b. Cost engineering c. Price engineering d. Quality control a. Value engineering

Mostrar más Leer menos
Institución
AIC
Grado
AIC











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
AIC
Grado
AIC

Información del documento

Subido en
5 de enero de 2026
Número de páginas
104
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

1/5/26, 9:40 PM AIC Exam




AIC ACTUAL FINAL EXAM 2026 -2027
Complete 250 Questions And Correct
Detailed Answers (Verified Answers)
|Already Graded A+ LATEST UPDATE!!



1. A project schedule has been updated. The activity placement of spread
footing concrete was originally scheduled to begin as early as day 10. The
activity duration
is 4 days. The actual start day was day 12. The original schedule had calculated total
float of 7 days for this activity. The recalculated total float for the activity, when
updated, would be...
A. 2 days
B. 5 days
C. 6 days
D. 9 days


B. 5 Days


2. The purpose of retainage is to encourage the general contractor to?


a. Submit payment request on time
b. Complete project per contract
c. Get construction materials on site quickly
d. Staff all areas of the project in a timely fashion


b. Complete project per contract



1/104

,1/5/26, 9:40 PM AIC Exam



3. A 'place concrete' activity requires the placement of 2080 cubic yards. If
the individual production rate is 2 cubic yards per work hour per person,
with a 10- person crew and 8 hour workday, how many days are needed to
complete this activity?
a.13
b.26
c.104
d.130


a. 13




4. What method is used to calculate activity duration?
a. Daily production rate divided by plan quantity
b. Plan quantity divided by crew rate
c. Plan quantity divided by daily production rate
d. Plan quantity dived by labor unit cost


c. plan quantity divided by daily perfromance



5. Which of the following can be identified from the initial schedule of values?
a.Vendors working on the project
b. Contractors proposed breakdown of the project cost
c. Profit margin of the applicant
d. Quality of work in place


b. contractors proposed breakdown of the project cost




2/104

,1/5/26, 9:40 PM AIC Exam



6. The architect has approved the rerouting of an HVAC through concrete slabs
in a building. To insure that activities are coordinated, a meeting should be called
by the field supervisor and the
a. HVAC subcontractor only
b. HVAC subcontractor and all other subcontractors
c. HVAC subcontractor and all other affected subcontractors
d. HVAC subcontractor and the architect engineer?


c. HVAC subcontractor and all other affected subcontractors




3/104

, 1/5/26, 9:40 PM AIC Exam



7. Concrete to be poured for 10 footings are 5 feet wide by 5 feet long by 2 feet
deep. How many cubic yards of concrete should the estimate be for this pour,
using a 10% waste factor.
a.14.8
b.16.3
c.18.5
d.20.3


d. 20.3




8. A topographical map is a drawing showing?
a.Subsurface soil conditions
b. A general profile view of the site
c. Contour lines and elevations
d. Cross sections along the length of the project.


c. Contour lines and elevations



9. The location of reinforcing steel used in a concrete member should be
placed where?
a. Shear is minimal
b. Concrete is in tension
c. Concrete is in compression
d. Center axis is located.


b.Concrete is in tension




4/104
$26.50
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
NURSEGENERAL Chamberlain College Of Nursing
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
80
Miembro desde
1 año
Número de seguidores
4
Documentos
8176
Última venta
1 semana hace
Homeland bookshop

It is a modern bookshop that provide accurate documents such as revision papers ,exams , notes , essays , summaries , flashcards and other study materials. Discover any material you want on my site and feel free to contact me at my email WELCOME ALL !!!! WELCOME ALL!!

4.3

12 reseñas

5
7
4
3
3
1
2
1
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes