AIC ACTUAL FINAL EXAM 2026 -2027
Complete 250 Questions And Correct
Detailed Answers (Verified Answers)
|Already Graded A+ LATEST UPDATE!!
1. A project schedule has been updated. The activity placement of spread
footing concrete was originally scheduled to begin as early as day 10. The
activity duration
is 4 days. The actual start day was day 12. The original schedule had calculated total
float of 7 days for this activity. The recalculated total float for the activity, when
updated, would be...
A. 2 days
B. 5 days
C. 6 days
D. 9 days
B. 5 Days
2. The purpose of retainage is to encourage the general contractor to?
a. Submit payment request on time
b. Complete project per contract
c. Get construction materials on site quickly
d. Staff all areas of the project in a timely fashion
b. Complete project per contract
1/104
,1/5/26, 9:40 PM AIC Exam
3. A 'place concrete' activity requires the placement of 2080 cubic yards. If
the individual production rate is 2 cubic yards per work hour per person,
with a 10- person crew and 8 hour workday, how many days are needed to
complete this activity?
a.13
b.26
c.104
d.130
a. 13
4. What method is used to calculate activity duration?
a. Daily production rate divided by plan quantity
b. Plan quantity divided by crew rate
c. Plan quantity divided by daily production rate
d. Plan quantity dived by labor unit cost
c. plan quantity divided by daily perfromance
5. Which of the following can be identified from the initial schedule of values?
a.Vendors working on the project
b. Contractors proposed breakdown of the project cost
c. Profit margin of the applicant
d. Quality of work in place
b. contractors proposed breakdown of the project cost
2/104
,1/5/26, 9:40 PM AIC Exam
6. The architect has approved the rerouting of an HVAC through concrete slabs
in a building. To insure that activities are coordinated, a meeting should be called
by the field supervisor and the
a. HVAC subcontractor only
b. HVAC subcontractor and all other subcontractors
c. HVAC subcontractor and all other affected subcontractors
d. HVAC subcontractor and the architect engineer?
c. HVAC subcontractor and all other affected subcontractors
3/104
, 1/5/26, 9:40 PM AIC Exam
7. Concrete to be poured for 10 footings are 5 feet wide by 5 feet long by 2 feet
deep. How many cubic yards of concrete should the estimate be for this pour,
using a 10% waste factor.
a.14.8
b.16.3
c.18.5
d.20.3
d. 20.3
8. A topographical map is a drawing showing?
a.Subsurface soil conditions
b. A general profile view of the site
c. Contour lines and elevations
d. Cross sections along the length of the project.
c. Contour lines and elevations
9. The location of reinforcing steel used in a concrete member should be
placed where?
a. Shear is minimal
b. Concrete is in tension
c. Concrete is in compression
d. Center axis is located.
b.Concrete is in tension
4/104