CTQP Final Estimates Level 1
Questions and Answers
1) A major function of the DOT is to carry out Construction and Reconstruction
programs to provide the public with adequate transportation service. - ANSWER-True
1) Multiple choice. Which of the following is NOT officially considered to be a "Contract
Document"?
A. Supplemental Agreements and Work Orders.
B. Notebooks and Estimates Procedure Manual.
C. Standard Specifications.
D. Construction Manual.
E. Answers B &D - ANSWER-E. Answer B & D
1) To document computations and summarize quantities, preprinted forms are available
for use in the:
A. Construction manual
B. Final Estimates Checklist.
C. Special provisions.
D. Computation Book.
E. None of the above. - ANSWER-D. Computation Book.
1) True or False. When checked and verified, final estimates serve as the basis for Final
Payment. - ANSWER-True
2) In which Manuals are the procedures for running check levels and cross sections
described?
A. Review and Administration Manual
B. Preparation & Documentation manual (P & D M)
C. Location & Survey Manual
D. CPAM
E. Both B and C - ANSWER-E. Both B and C
2) Multiple choice. Between printings of the Standard Specifications, what does the
Department publish to identify and describe changes in the Specifications?
A. CPAM
B. Supplemental Specifications
C. Work orders
D. Specifications Changes - ANSWER-B Supplemental Specifications
2) Multiple choice. Which of the following sets for the Department's methods and
Procedures for preparing and checking final estimates?
A. Construction Inspection Mathematics
B. Project Engineer
, C. Preparation and Documentation Manual
D. CPAM - ANSWER-C. Preparation and Documentation Manual
2) Which of the following must be summarized on a preprinted form or other summary
sheet?
A. Wage Rates.
B. Job Correspondence
C. Types of equipment
D Pay items
E. None of the above - ANSWER-D. Pay items
3) Multiple choice. Select the correct sequence of documents in order of precedence,
with the document highest in authority listed first.
A. Contract Plans, Development Specifications, Standard Specifications, Special
Provisions, Technical Special Provisions, Supplemental Specifications, Design
Standards.
B. Design Standards, Special Provisions, Technical Special Provisions, Supplemental
Specifications, Contract Plans, development Specifications, Standard Specifications.
C. Special Provisions, Technical Special Provisions, Contract Plans, Design Standards,
Development Specifications, Supplemental Specifications, Standard Specifications.
D. Supplemental Specifications, Special Provisions, Contract Plans, Development
Specifications, Standards Specifications, Technical Special Provisions, Design
Standards. E. None of the above. - ANSWER-C. Special Provisions, Technical Special
Provisions, Contract Plans, Design Standards, Development Specifications,
Supplemental Specifications, Standard Specifications.
3) Square yard items of asphaltic concrete and lime rock can be calculated on the same
form. True or false? - ANSWER-True
3) To pay for the work performed by Contractors, progress and Final Estimates are
needed. True or False? - ANSWER-True
4) Forms should be inserted in the computation book in the same sequence that the
items are listed in the contract. True and False - ANSWER-True
5) Total quantities from the individual computation forms are summarized on the Pay
Item Summary Sheet. True or False. - ANSWER-True
7) Even though three financial project ID's are included in the same contract, you should
combine information from all three jobs in the same notebook. True or False -
ANSWER-False
A detailed page of Notebook contents should begin on the first lined page( page 1) of a
field book. True or false? - ANSWER-True
Questions and Answers
1) A major function of the DOT is to carry out Construction and Reconstruction
programs to provide the public with adequate transportation service. - ANSWER-True
1) Multiple choice. Which of the following is NOT officially considered to be a "Contract
Document"?
A. Supplemental Agreements and Work Orders.
B. Notebooks and Estimates Procedure Manual.
C. Standard Specifications.
D. Construction Manual.
E. Answers B &D - ANSWER-E. Answer B & D
1) To document computations and summarize quantities, preprinted forms are available
for use in the:
A. Construction manual
B. Final Estimates Checklist.
C. Special provisions.
D. Computation Book.
E. None of the above. - ANSWER-D. Computation Book.
1) True or False. When checked and verified, final estimates serve as the basis for Final
Payment. - ANSWER-True
2) In which Manuals are the procedures for running check levels and cross sections
described?
A. Review and Administration Manual
B. Preparation & Documentation manual (P & D M)
C. Location & Survey Manual
D. CPAM
E. Both B and C - ANSWER-E. Both B and C
2) Multiple choice. Between printings of the Standard Specifications, what does the
Department publish to identify and describe changes in the Specifications?
A. CPAM
B. Supplemental Specifications
C. Work orders
D. Specifications Changes - ANSWER-B Supplemental Specifications
2) Multiple choice. Which of the following sets for the Department's methods and
Procedures for preparing and checking final estimates?
A. Construction Inspection Mathematics
B. Project Engineer
, C. Preparation and Documentation Manual
D. CPAM - ANSWER-C. Preparation and Documentation Manual
2) Which of the following must be summarized on a preprinted form or other summary
sheet?
A. Wage Rates.
B. Job Correspondence
C. Types of equipment
D Pay items
E. None of the above - ANSWER-D. Pay items
3) Multiple choice. Select the correct sequence of documents in order of precedence,
with the document highest in authority listed first.
A. Contract Plans, Development Specifications, Standard Specifications, Special
Provisions, Technical Special Provisions, Supplemental Specifications, Design
Standards.
B. Design Standards, Special Provisions, Technical Special Provisions, Supplemental
Specifications, Contract Plans, development Specifications, Standard Specifications.
C. Special Provisions, Technical Special Provisions, Contract Plans, Design Standards,
Development Specifications, Supplemental Specifications, Standard Specifications.
D. Supplemental Specifications, Special Provisions, Contract Plans, Development
Specifications, Standards Specifications, Technical Special Provisions, Design
Standards. E. None of the above. - ANSWER-C. Special Provisions, Technical Special
Provisions, Contract Plans, Design Standards, Development Specifications,
Supplemental Specifications, Standard Specifications.
3) Square yard items of asphaltic concrete and lime rock can be calculated on the same
form. True or false? - ANSWER-True
3) To pay for the work performed by Contractors, progress and Final Estimates are
needed. True or False? - ANSWER-True
4) Forms should be inserted in the computation book in the same sequence that the
items are listed in the contract. True and False - ANSWER-True
5) Total quantities from the individual computation forms are summarized on the Pay
Item Summary Sheet. True or False. - ANSWER-True
7) Even though three financial project ID's are included in the same contract, you should
combine information from all three jobs in the same notebook. True or False -
ANSWER-False
A detailed page of Notebook contents should begin on the first lined page( page 1) of a
field book. True or false? - ANSWER-True