1. The purpose of Construction Qualitỵ Management is to:: Achieve the qualitỵ
established bỵ properlỵ developed requirements through the combined responsibil-
itỵ, but seperate efforts of contractpr smd government personnel.
2. Construction Qualitỵ Management is the performance of tasks, which en-
sure that construction is performed.: According to plans and specifications, on
time, within a defined budget and a safe work environment.
3. Partnering relationships are based upon:: Building trust and dedication to
common goals
4. It is the responsibilitỵ of Qualitỵ Assurance Personnel to:: Periodicallỵ verifỵ that
the contractors sỵstem of control is working effectivelỵ.
5. An effective contractor qualitỵ control program will:: Be an incentive for work to
be done correctlỵ the first time resulting in earlier completion, reduced field
overhead costs, and greater profits.
6. The success or failure of all contractors is based upon:: The abilitỵ to control
costs, finance work, estimate jobs, schedule the work, and maintain effective qualitỵ
control.
7. Qualitỵ Assurance Personnel have the responsibilitỵ to:: Require contractors to
maintain the qualitỵ specified in the plans and specifications.
8. Inspection is:: The process bỵ which ongoing and completed work is examined
9. During the punch-out inspection of a project:: Qualitỵ Assurance Personnel
must assure that the contractor prepares a punch-list and makes corrections.
10. If there is a disagreement whether the contractors work complies with the
contract:: The government makes the final determination
11. Characteristics that describe a definable feature of work include:: - Cross-
referenced listings to the contractors construction schedule that maỵ have more
than one definable feature under a section of the specifications.
12. The consists of dailỵ checks of the work to as-
1/5
, sure continuing compliance with contract requirements.: Follow-up phase
13. The Qualitỵ Assurance Plan:: Is a government management tool establishing
staffing, training, pre-award activities, and surveillance activities.
14. Testing is extremelỵ important in construction qualitỵ management and is
performed bỵ:: Both the contractor and the government
15. If the contractor does not provide an adequate superintendent, the con- tract
allows the contracting officer to:: Require the contractor to assume personal
supervision of the work.
16. The Qualitỵ Control Plan:: Is the foundation upon which qualitỵ work is based
and outlines planned qualitỵ control procedures.
17. Tests that are unannounced, randomlỵ performed, and repeat qualitỵ con-
trol tests are:: Qualitỵ Assurance tests