FDNY s12 Exam w ith pr ecise detailed |! |! |! |! |! |!
an sw er s
During an operational test of a foam water sprinkler system, if the nozzles are
|! |! |! |! |! |! |! |! |! |! |! |! |!
plugged what color tag is used?
|! |! |! |! |! |!
Red
Steel water storage tanks without corrosive protection are to be inspected how
|! |! |! |! |! |! |! |! |! |! |!
often?
|!
3 Years
|!
A sprinkler head with a white frame has a temperature rating of?
|! |! |! |! |! |! |! |! |! |! |!
175 - 225°F |! |!
The weekly test of a Diesel fire pump is how long?
|! |! |! |! |! |! |! |! |! |!
30 minutes |!
The weekly test of an electric fire pump is how long?
|! |! |! |! |! |! |! |! |! |!
10 minutes |!
Upon inspection of a sprinkler system, if the hydraulic nameplate is missing
|! |! |! |! |! |! |! |! |! |! |! |!
what color tag is used? |! |! |! |!
Yellow
When inspecting a preaction system, if the electrical components are not in
|! |! |! |! |! |! |! |! |! |! |! |!
service what color tag is used? |! |! |! |! |!
Red
Vane type water flow devices shall be tested how often?
|! |! |! |! |! |! |! |! |!
Semi-annually
,Proper number of spare heads and wrenches shall be inspected how often?
|! |! |! |! |! |! |! |! |! |! |!
Annually
The temperature rating of a sprinkler head with a green glass bulb is?
|! |! |! |! |! |! |! |! |! |! |! |!
175 - 225°F
|! |!
When inspecting a sprinkler system if the spare sprinkler cabinet is missing
|! |! |! |! |! |! |! |! |! |! |! |!
what color tag should be used?
|! |! |! |! |!
Yellow
On a dry pipe sprinkler head if no tests were conducted in 12 years what
|! |! |! |! |! |! |! |! |! |! |! |! |! |! |!
color tag should be used?
|! |! |! |!
Orange
Red Tag |!
Impairment (Notify FDNY, shall be fixed immediately) |! |! |! |! |! |!
Orange Tag |!
Critical Deficiency (Notify FDNY if not fixed after 30 days)
|! |! |! |! |! |! |! |! |!
Yellow Tag |!
Non-critical Deficiency (Notify FNDY if not fixed after 30 days)
|! |! |! |! |! |! |! |! |!
Green Tag |!
System fully operational without defects
|! |! |! |!
How often shall the stem of an OS&Y Valve be lubricated
|! |! |! |! |! |! |! |! |! |!
Annually
The 3 year dry pipe trip test is to be performed by whom?
|! |! |! |! |! |! |! |! |! |! |! |!
MP & MFSPC
|! |!
Fire department connections are to be inspected how often?
|! |! |! |! |! |! |! |!
Quarterly
,Water motor gongs are to be tested how often?
|! |! |! |! |! |! |! |!
Quarterly
In a water spray fixed system inspection if the strainer is found corroded
|! |! |! |! |! |! |! |! |! |! |! |! |!
what color tag is required?|! |! |! |!
Yellow
A sprinkler head with a red frame has a temperature classification of?
|! |! |! |! |! |! |! |! |! |! |!
Extra High (325 - 375°F) |! |! |! |!
The Hydraulic name plate shall be inspected how often?
|! |! |! |! |! |! |! |!
Quarterly
What color tag is required when sprinkler heads are found to be lightly
|! |! |! |! |! |! |! |! |! |! |! |! |!
corroded?
Orange
Obstructions in sprinkler systems shall be investigated how often? |! |! |! |! |! |! |! |!
5 Years
|!
What color tag is required when the circuit breakers on a special service
|! |! |! |! |! |! |! |! |! |! |! |! |!
pump are over 2 years old? |! |! |! |! |!
Orange
What color tag is required when sprinkler heads made prior to 1920 have not
|! |! |! |! |! |! |! |! |! |! |! |! |! |!
been replaced? |!
Orange, notify FDNY after 30 days |! |! |! |! |!
Orange/Red bulb temperature |! |!
135 - 170°F |! |!
Yellow or Green Bulb temperature |! |! |! |!
175 - 225°F |! |!
, Blue Bulb temperature
|! |!
250 - 300°F
|! |!
Purple Bulb temperature |! |!
325 - 375°F
|! |!
Black Bulb with Green Frame temperature
|! |! |! |! |!
400 - 475°F
|! |!
Black Bulb with Orange Frame Temperature
|! |! |! |! |!
500 - 650°F
|! |!
The temperature for water tanks shall not be less than
|! |! |! |! |! |! |! |! |!
40°F (4°C) |!
Tanks without supervised water level alarms shall be inspected
|! |! |! |! |! |! |! |!
Monthly
Tanks with supervised water level alarms shall be inspected
|! |! |! |! |! |! |! |!
Quarterly
Records of all system inspections, tests, servicing, and maintenance shall be
|! |! |! |! |! |! |! |! |! |! |!
kept on premises for
|! |! |!
A minimum of 3 years
|! |! |! |!
The building owner shall assign an ___________ to comply with city
|! |! |! |! |! |! |! |! |! |! |!
requirements
Impairment Coordinator |!
White Disc, Red Tag |! |! |!
System fully out of service |! |! |! |!
Blue Disc, Red Tag
|! |! |!
System partially out of service |! |! |! |!
an sw er s
During an operational test of a foam water sprinkler system, if the nozzles are
|! |! |! |! |! |! |! |! |! |! |! |! |!
plugged what color tag is used?
|! |! |! |! |! |!
Red
Steel water storage tanks without corrosive protection are to be inspected how
|! |! |! |! |! |! |! |! |! |! |!
often?
|!
3 Years
|!
A sprinkler head with a white frame has a temperature rating of?
|! |! |! |! |! |! |! |! |! |! |!
175 - 225°F |! |!
The weekly test of a Diesel fire pump is how long?
|! |! |! |! |! |! |! |! |! |!
30 minutes |!
The weekly test of an electric fire pump is how long?
|! |! |! |! |! |! |! |! |! |!
10 minutes |!
Upon inspection of a sprinkler system, if the hydraulic nameplate is missing
|! |! |! |! |! |! |! |! |! |! |! |!
what color tag is used? |! |! |! |!
Yellow
When inspecting a preaction system, if the electrical components are not in
|! |! |! |! |! |! |! |! |! |! |! |!
service what color tag is used? |! |! |! |! |!
Red
Vane type water flow devices shall be tested how often?
|! |! |! |! |! |! |! |! |!
Semi-annually
,Proper number of spare heads and wrenches shall be inspected how often?
|! |! |! |! |! |! |! |! |! |! |!
Annually
The temperature rating of a sprinkler head with a green glass bulb is?
|! |! |! |! |! |! |! |! |! |! |! |!
175 - 225°F
|! |!
When inspecting a sprinkler system if the spare sprinkler cabinet is missing
|! |! |! |! |! |! |! |! |! |! |! |!
what color tag should be used?
|! |! |! |! |!
Yellow
On a dry pipe sprinkler head if no tests were conducted in 12 years what
|! |! |! |! |! |! |! |! |! |! |! |! |! |! |!
color tag should be used?
|! |! |! |!
Orange
Red Tag |!
Impairment (Notify FDNY, shall be fixed immediately) |! |! |! |! |! |!
Orange Tag |!
Critical Deficiency (Notify FDNY if not fixed after 30 days)
|! |! |! |! |! |! |! |! |!
Yellow Tag |!
Non-critical Deficiency (Notify FNDY if not fixed after 30 days)
|! |! |! |! |! |! |! |! |!
Green Tag |!
System fully operational without defects
|! |! |! |!
How often shall the stem of an OS&Y Valve be lubricated
|! |! |! |! |! |! |! |! |! |!
Annually
The 3 year dry pipe trip test is to be performed by whom?
|! |! |! |! |! |! |! |! |! |! |! |!
MP & MFSPC
|! |!
Fire department connections are to be inspected how often?
|! |! |! |! |! |! |! |!
Quarterly
,Water motor gongs are to be tested how often?
|! |! |! |! |! |! |! |!
Quarterly
In a water spray fixed system inspection if the strainer is found corroded
|! |! |! |! |! |! |! |! |! |! |! |! |!
what color tag is required?|! |! |! |!
Yellow
A sprinkler head with a red frame has a temperature classification of?
|! |! |! |! |! |! |! |! |! |! |!
Extra High (325 - 375°F) |! |! |! |!
The Hydraulic name plate shall be inspected how often?
|! |! |! |! |! |! |! |!
Quarterly
What color tag is required when sprinkler heads are found to be lightly
|! |! |! |! |! |! |! |! |! |! |! |! |!
corroded?
Orange
Obstructions in sprinkler systems shall be investigated how often? |! |! |! |! |! |! |! |!
5 Years
|!
What color tag is required when the circuit breakers on a special service
|! |! |! |! |! |! |! |! |! |! |! |! |!
pump are over 2 years old? |! |! |! |! |!
Orange
What color tag is required when sprinkler heads made prior to 1920 have not
|! |! |! |! |! |! |! |! |! |! |! |! |! |!
been replaced? |!
Orange, notify FDNY after 30 days |! |! |! |! |!
Orange/Red bulb temperature |! |!
135 - 170°F |! |!
Yellow or Green Bulb temperature |! |! |! |!
175 - 225°F |! |!
, Blue Bulb temperature
|! |!
250 - 300°F
|! |!
Purple Bulb temperature |! |!
325 - 375°F
|! |!
Black Bulb with Green Frame temperature
|! |! |! |! |!
400 - 475°F
|! |!
Black Bulb with Orange Frame Temperature
|! |! |! |! |!
500 - 650°F
|! |!
The temperature for water tanks shall not be less than
|! |! |! |! |! |! |! |! |!
40°F (4°C) |!
Tanks without supervised water level alarms shall be inspected
|! |! |! |! |! |! |! |!
Monthly
Tanks with supervised water level alarms shall be inspected
|! |! |! |! |! |! |! |!
Quarterly
Records of all system inspections, tests, servicing, and maintenance shall be
|! |! |! |! |! |! |! |! |! |! |!
kept on premises for
|! |! |!
A minimum of 3 years
|! |! |! |!
The building owner shall assign an ___________ to comply with city
|! |! |! |! |! |! |! |! |! |! |!
requirements
Impairment Coordinator |!
White Disc, Red Tag |! |! |!
System fully out of service |! |! |! |!
Blue Disc, Red Tag
|! |! |!
System partially out of service |! |! |! |!