Introduction
This file contains 300+ pages and about 700 questions and answers covering all of the sections of the textbook.
j j j j j j j j j j j j j j j j j j
Whether you are seeking a PMI certification or trying to learn about project management from an introductory
j j j j j j j j j j j j j j j j
point of view – you fill find that this file contains questions across the board in terms of difficulty (from easy to
j j j j j j j j j j j j j j j j j j j j j j j
hard).
If you are a student seeking a PMI certification, you will find that many of the questions contained in this file are
j j j j j j j j j j j j j j j j j j j j j j
adapted from ―PMI Prep‖ textbooks. Chances are, if you can do and understand all of the questions in this
j j j j j j j j j j j j j j j j j j j
file, you should have an easy time of it when writing your PMI certification exam.
j j j j j j j j j j j j j j
If you are interested in doing questions by topic, press CTRL + F, and this will bring up the Reader Search
j j j j j j j j j j j j j j j j j j j j j
pane. Input the topic in the Search field, press ENTER and Reader will return a list of all the instances of that
j j j j j j j j j j j j j j j j j j j j j j
topic found in this file. If you are interested in doing questions by textbook section, use the Bookmarks feature
j j j j j j j j j j j j j j j j j j j
in the this file to navigate to a particular section of questions.
j j j j j j j j j j j
When certain questions overlap textbook topics, the question sections have been designated as such (e.g., there
j j j j j j j j j j j j j j j j
is an Initiation/Planning Phase section with questions that cover both phases) or when certain questions are
j j j j j j j j j j j j j j j j
very topic specific, they have been placed in a section designated as such (e.g., Quality).
j j j j j j j j j j j j j j
There are fill in the blank, multiple choice, case style etc. questions in this file – this has been done to give you
j j j j j j j j j j j j j j j j j j j j j j j
a broader experience in problem solving.
j j j j j
The answers follow the questions either immediately or on a following page. Many questions have sub
j j j j j j j j j j j j j j j j
questions to them (they are usually numbered numerically as well). The question numbers are left justified
j j j j j j j j j j j j j j j j
with the margin and in the following format:
j j j j j j j
1. A scope change is defined as a: j j j j j j
If you can not answer a question on your own and/or by referring to the textbook, then you need to search for
j j j j j j j j j j j j j j j j j j j j j j
the information elsewhere and/or think on your own – this was done deliberately to ―challenge‖ you (i.e., the
j j j j j j j j j j j j j j j j j j
author‘s way of encouraging you to be more proactive and creative). Of course, every question in this file has an
j j j j j j j j j j j j j j j j j j j j
answer – in case you get ―stuck.‖ j j j j j j
,Questions and Answers Page 3 of 348
InitiationPhase j
2. A series of activities to create a unique product or service by a specific date is best described as which one of
j j j j j j j j j j j j j j j j j j j j j j
the following? j
A. A program j
B. An operation j
C. A project j
D. A subprojectj
Answer: C j
A is incorrect, because a program is a collection of projects with a common cause. B is not a valid choice as
j j j j j j j j j j j j j j j j j j j j j j
operations are ongoing activities. Subprojects (answer D) represent portions of a project broken off into smaller
j j j j j j j j j j j j j j j j
endeavors.
3. In what process is the project manager selected to manage a project?
j j j j j j j j j j j
A. Initiation
B. Planning
C. Controlling
D. Design
Answer: A j
B, C, and D are incorrect. Note that the design process is not one of the five project management processes.
j j j j j j j j j j j j j j j j j j j j
Design is often a project process that could fall into the planning process. Recall that the five processes in the
j j j j j j j j j j j j j j j j j j j j
project management life cycle are: Initiation, Planning, Execution, Control, and Closure.
j j j j j j j j j j
4. Which of the following is not a project management process?j j j j j j j j j
A. Initiating
B. Planning
C. Controlling
D. Designing
Answer: D j
A, B, and C are valid project management lifecycle phases, so they are an incorrect choice for this question.
j j j j j j j j j j j j j j j j j j
5. A program is which one of the following?
j j j j j j j
A. A very large, complex project
j j j j
B. A collection of small projects with a common goal
j j j j j j j j
C. A collection of projects with a common cause
j j j j j j j
D. A collection of subprojects with a common customer
j j j j j j j
Answer: C j
A is incorrect because a program is a collection of projects, not just one large, complex project. B is incorrect
j j j j j j j j j j j j j j j j j j j j
because programs are not made up of just small projects. D is incorrect since projects with a common customer
j j j j j j j j j j j j j j j j j j j
do not necessitate a program.
j j j j
, Questions and Answers Page 4 of 348
6. Of the following, which is the most important person involved with a project?
j j j j j j j j j j j j
A. The project manager j j
B. The project sponsor j j
C. The CEO j
D. The customer j
Answer: D j
A is incorrect, because the project manager manages the project for the customer. B is incorrect since the
j j j j j j j j j j j j j j j j j j
project sponsor authorizes the project. C is incorrect because the CEO may not even know about the project
j j j j j j j j j j j j j j j j j j
and even then he would be interested in the success of the project for the customer.
j j j j j j j j j j j j j j j
7. You are a project manager for your organization. Management has asked you to help them determine
j j j j j j j j j j j j j j j j
which projects should be selected for implementation. In a project selection model, the most important
j j j j j j j j j j j j j j j
factor is which one of the following? j j j j j j
A. Business needs j
B. Type of constraints j j
C. Budget
D. Schedule
Answer: A. j
B is incorrect, as the project constraints are typically not an issue when a project is selected, the feasibility of a
j j j j j j j j j j j j j j j j j j j j j
project to operate within the project constraints may be an issue, however. C, the project budget, is incorrect as
j j j j j j j j j j j j j j j j j j
the project budget is a project constraint. D is incorrect, as the project schedule is also a constraint.
j j j j j j j j j j j j j j j j j j
8. The primary purpose of your project plan is:
j j j j j j j
A. To define the work to be completed to reach the project end date.
j j j j j j j j j j j j
B. To define the work needed in each phase of the project life cycle.
j j j j j j j j j j j j
C. To prevent any changes to the scope.
j j j j j j
D. To provide accurate communication for the project team, project sponsor, and stakeholders.
j j j j j j j j j j j
Answer: D. j
A and B are incorrect, as they do not define the primary purpose of the project plan. C is also incorrect; the
j j j j j j j j j j j j j j j j j j j j j j
project plan is intended not to prevent changes, but to communicate.
j j j j j j j j j j
9. The project plan provides a baseline for several things. Which one of the following does the project plan
j j j j j j j j j j j j j j j j j j
not provide a baseline for? j j j j
A. Technical performance j
B. Cost
C. Schedule
D. Control
Answer: D. j
Choices A, B, and C describe the project baselines contained within the project plan.
j j j j j j j j j j j j j