Q1: Which type of document provides the detailed drawings and specifications during the design
phase?
A. Contract Documents
B. Design Phase Documents
C. Closeout Documents
D. Bidding Documents
Answer: B
Explanation: Design phase documents include the drawings and specifications that communicate design
intent and technical details.
Q2: What is the primary purpose of construction documents in a project?
A. To decorate the site
B. To guide project execution and ensure clarity
C. To replace verbal instructions
D. To serve as marketing material
Answer: B
Explanation: Construction documents are critical for guiding the construction process and ensuring that
all parties understand the project details.
Q3: Which document phase is responsible for preparing bid packages?
A. Design Phase
B. Bidding and Procurement Phase
C. Construction Phase
D. Closeout Phase
Answer: B
Explanation: Bid packages are assembled during the bidding and procurement phase to invite contractor
proposals.
Q4: What is the significance of document control during a project’s lifecycle?
A. It minimizes printing costs
B. It manages revisions and ensures accuracy
C. It delays the project schedule
D. It only applies to digital documents
Answer: B
Explanation: Document control ensures that all revisions are managed and that everyone uses the most
current, accurate information.
Q5: Which of the following is NOT a key type of construction document?
A. Drawings
B. Specifications
C. Contracts
D. Promotional Brochures
Answer: D
Explanation: Promotional brochures are not part of the technical documents used to guide construction.
,Q6: In construction, which document type is used to formally define the legal and binding agreement
between parties?
A. Drawings
B. Specifications
C. Contract Documents
D. Submittals
Answer: C
Explanation: Contract documents are the legally binding agreements outlining the responsibilities and
obligations of the involved parties.
Q7: Which contract type is characterized by a fixed price regardless of actual costs?
A. Cost-Plus
B. Time and Materials
C. Lump-Sum
D. Unit Price
Answer: C
Explanation: A lump-sum contract fixes the total price for the entire project regardless of cost
fluctuations.
Q8: What do general conditions in a contract typically address?
A. Aesthetic design elements
B. Standard rights and obligations of the parties
C. Specific product details
D. Marketing strategies
Answer: B
Explanation: General conditions outline the basic legal rights, responsibilities, and administrative
provisions for the project.
Q9: Which document is most likely to include drawing scales, symbols, and notations?
A. Contract Documents
B. Specifications
C. Construction Drawings
D. Project Schedules
Answer: C
Explanation: Construction drawings contain scales, symbols, and notations that communicate design and
construction details.
Q10: What is the purpose of change orders during the construction phase?
A. To delay project completion
B. To document approved changes in the work scope
C. To reduce the quality of work
D. To finalize the project closeout
Answer: B
Explanation: Change orders formally record any approved modifications to the scope, schedule, or cost
during construction.
,Q11: Which document serves as a formal request for information clarifications during bidding?
A. Submittals
B. Request for Information (RFI)
C. Punch List
D. Closeout Document
Answer: B
Explanation: An RFI is used by bidders to obtain clarifications on bid documents before submitting their
proposals.
Q12: What role does the construction manager typically play in contract administration?
A. Designing the building aesthetics
B. Overseeing day-to-day operations and communication
C. Financing the project
D. Performing the site cleanup
Answer: B
Explanation: The construction manager coordinates daily operations and ensures that contract
requirements are met.
Q13: In project scheduling, what is the ‘critical path’?
A. The longest sequence of tasks determining project duration
B. A shortcut through the project plan
C. The list of optional tasks
D. The path with the highest cost
Answer: A
Explanation: The critical path is the sequence of tasks that determines the overall project duration; any
delay in these tasks will delay the entire project.
Q14: Which technique is used to manage project delays and disputes?
A. Ignoring schedule risks
B. Developing a risk management plan
C. Eliminating all change orders
D. Outsourcing contract administration
Answer: B
Explanation: A risk management plan helps identify, assess, and mitigate delays and disputes in a
project.
Q15: What is the main objective of contract closeout procedures?
A. To launch a new project
B. To verify that all contractual obligations have been met
C. To design new specifications
D. To increase the project budget
Answer: B
Explanation: Contract closeout procedures ensure that all work is completed, all documents are
finalized, and all contractual obligations are satisfied.
Q16: Which of the following best describes the term “document lifecycle” in construction?
A. The period during which documents are printed
, B. The continuous process from document creation to project completion
C. The time taken to read a document
D. The storage period after project completion only
Answer: B
Explanation: The document lifecycle refers to the entire process of creating, managing, revising, and
archiving documents throughout a project.
Q17: What is one of the primary benefits of well-organized construction documents?
A. They eliminate the need for inspections
B. They reduce miscommunication and costly errors
C. They increase material costs
D. They simplify design aesthetics
Answer: B
Explanation: Organized documents improve clarity and coordination, thereby reducing errors and
miscommunications during construction.
Q18: Which document typically contains the technical details such as material specifications and
installation methods?
A. Contract Documents
B. Construction Drawings
C. Specifications
D. Submittals
Answer: C
Explanation: Specifications provide detailed technical requirements and methods necessary for proper
installation and quality assurance.
Q19: In the context of construction contracts, what are “special conditions”?
A. Additional requirements that modify the general conditions
B. Standard design guidelines
C. Routine maintenance instructions
D. Marketing conditions for the project
Answer: A
Explanation: Special conditions are customized provisions that tailor the standard contract to the
specific needs of a project.
Q20: What is a primary purpose of submittals during construction?
A. To replace the need for drawings
B. To confirm that materials meet specified requirements
C. To serve as the contract agreement
D. To advertise construction products
Answer: B
Explanation: Submittals, such as shop drawings and product data, verify that the contractor’s products
and methods meet the project’s specifications.
Q21: Which party is primarily responsible for ensuring the timely review of submittals?
A. The contractor
B. The supplier