UST Service
A
VI
Technician: Final
TU
Exam 2 Questions
IS
M
and Answers
O
Correctly Solved
A
N
JP
2025!!
,UDC was required at time of installation for all systems installed after?
January 1, 2000
July 1, 2005, service techs shall possess or work under someone who has a current
certification indicating he or she has passed the?
ICC UST Service Technician Exam
A
ICC cert must be renewed every?
24 months
VI
Service techs must possess or be employed by a person who has the appropriate
TU
contractor's license unless?
The individual has a tank testing license
IS
Service tech is defined by any individual who?
Tests UST monitoring equipment, trouble shoots UST systems, and/or installs UST
monitoring equipment.
M
If the manufacturer training no longer exist, the local agency may?
O
Approve comparable alternate training .
A
UST includes?
Tank and connected piping
N
JP
What is considered a UST?
A petroleum underground storage tank.
What UST system meets the requirements for secondary containment?
Doubled wall tanks
,According to title 23; the following piping components if installed after July 1, 1987 must
have secondary containment.
Pressured product piping
What is considered "pipe" on tanks installed after July 1, 2003?
Pressured product piping and below ground vapor recovery.
A
Under dispenser containment (UDC) was required for all existing UST systems by
December 31, 2003
VI
What system is for exchanging gas vapors in a storage tank and product in a fuel
TU
delivery truck
Stage 1 vapor recovery
IS
Which approved method for non-visual monitoring for existing UST systems.
Statistical Inventory Reconciliation (SIR)
M
ATG must be capable for detecting a release of?
0.2 gallons per hour
O
What is no longer an approved method for non-visual monitoring on existing UST
A
systems?
Manual inventory reconciliation.
N
JP
Automatic line leak detectors installed on underground piping with secondary
containment shall be capable of detecting a leak of ?
3 gallons per hour at 10 psi
How often should ATG be programmed to test the tank?
At least monthly
, According to PEI RP 300, a combustible gas can be used to?
Detect vapor leaks in a vapor recovery system.
According to PEI RP 300, a written scope of work for vapor recovery installation should
include?
Construction plans
A
Positive shut off overfill protection device must stop the flow of fuel when the tank is no
more then?
VI
95% full
TU
According to Executive Order (EO) VR 201-A , what could cause a nozzle shut off
mechanism or malfunction?
Depended filter seal damage IS
According to VR 201-A, breakaway reconnection must be?
Logged in GDF log
M
According to PEI RP 300 what is an INCORRECT method of documenting piping
O
location?
Sketching a diagram on the inside cover of vapor recovery equipment manual
A
According to PEI RP 300 as built drawing or pictures of the underground pipping and
N
other components shall be_________.
maintained as long as UST is in service.
JP
According to EO VR 101-E maintenance records are required to include what?
Name and Designated UST Operator.
The Phil-Tite EVR Phase 1 system require that vapor vent pipes at any UST system be
Used with no more than 3 p/v valves