100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4,6 TrustPilot
logo-home
Exam (elaborations)

Subgrade & Base Inspection – FDOT Exam Questions with Complete Solutions

Rating
-
Sold
-
Pages
13
Grade
A+
Uploaded on
04-03-2025
Written in
2024/2025

Subgrade & Base Inspection – FDOT Exam Questions with Complete Solutions

Institution
FDOT
Course
FDOT









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
FDOT
Course
FDOT

Document information

Uploaded on
March 4, 2025
Number of pages
13
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Subgrade & Base Inspection – FDOT
Exam Questions with Complete
Solutions
List three general requirements for all equipment used in subgrade operations: -
Answer--Be in good condition
-Operate safely
-Produce desired results

How are spread distances marked? - Answer-Stakes

A certain transport holds 42,360 pounds of cement. The design application rate is 30
pounds. The subgrade is 21 feet wide. What is the spread distance for this particular
transport? __ (to the nearest foot) - Answer-605 feet

What should you collect from each cement transport as it arrives at the job? - Answer-
Delivery ticket

Cement should NOT be spread:

__A. during rain
__B. at steady air temperature of 35 degrees Fahrenheit
__C. in high winds
__D. at the design application rate - Answer-(__A.) during rain
(__B.) at steady air temperature of 35 degrees Fahrenheit
(__C.) in high winds
__D. at the design application rate

When cement treatment follows lime treatment, what minimum amount of time should
pass between the completion of the lime treatment and the beginning of the cement
treatment? - Answer-7 days

A canvas check of the cement spread is performed. The canvas plus cement weigh
38.8 pounds. The canvas alone weighs 4.5 pounds. What is the application rate? -
Answer-34.3 lbs/ sq. yd

When possible, the entire subgrade width should be mixed in:

__A. three or more passes
__B. a single operation
__C. five minutes
__D. a central plant - Answer-__A. three or more passes
(__B.) a single operation

, __C. five minutes
__D. a central plant

May subgrade mixing be done to full depth in one course -- if mixing and density
requirements can be met? - Answer-Yes

Normally, mixing must begin within __ after the cement is spread. - Answer-30

What can be done to the subgrade whenever the moisture content exceeds the
specified level? - Answer-It can be aerated by remixing or blending

By the central plant method, all the materials must be mixed for at least - Answer-30
seconds

What is the time limit for placement of the central-plant mixture in adjacent passes? -
Answer-30 minutes

Is the dumping of soil-cement mixtures in piles or windrows on the subgrade
acceptable? - Answer-No

What should you use to check the depth of cement-treated subgrades? - Answer--
Smooth metal rod
-Jack
-Stringline

What tool should you use in checking for uniformity of mixing - Answer-Posthole digger

In a mixed, cement-treated subgrade, there should be no soil particles larger than __ -
Answer-1'' in diameter

For cement-treated subgrades, where are the maximum density and optimum moisture
values determined?

Who makes these determinations? - Answer--In the field

-Inspector

When is the earliest that compaction can be started after mixing has been completed?
___ When is the latest? ___ - Answer-Immediately; Not later than 60 minutes

Cement-treated subgrades must be compacted to at least __ percent of the maximum
density. - Answer-95

Areas of the subgrade that need additional soil-cement mixture in order to comply with
the plans must first be lightly __. - Answer-Scarified
R265,44
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached


Document also available in package deal

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
lectknancy Boston University
Follow You need to be logged in order to follow users or courses
Sold
289
Member since
2 year
Number of followers
28
Documents
26010
Last sold
15 hours ago

3,6

57 reviews

5
23
4
10
3
11
2
3
1
10

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can immediately select a different document that better matches what you need.

Pay how you prefer, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card or EFT and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions