T/F: In the Contractor Quality Control (CQC) inspection process implemented by some federal
agencies, the Contractor must organize and maintain an inspection system. - Answer✔True
T/F: On a multiple-prime project, the owner is responsible for coordinating the various trade
contractors with whom it has contracted. - Answer✔True
T/F: The design-build process may face some legal barriers when tried to be implemented in the
public sector. - Answer✔True
Chronological order of the 5 steps of initiating a construction project. - Answer✔Advertise for
bids
Open bids
Award contract
Sign the contract
Issue notice to proceed
T/F: In fast-track projects with multiple contractors, the services of a professional construction
management firm (Agency CM) are essential. - Answer✔True
Which phases can a professional construction management firm (agency CM) participate in? -
Answer✔Conception
Program Planning
Design
Construction
Closeout
What is the order of routing submittals from subcontractor to designer? - Answer✔Subcontractor
General Contractor
Resident Project Representative
Project Manager