Guide
1. Which of the following techniques can be used to model the rationale of a
change?
A. Roles and Permissions Matrix
B. Organizational modelling
C. Business capability analysis
D. Decision modelling - correct answers✅✅D. Decision modelling
Explanation: BABoK V3.0 - Section 7.1.4.1 - Model Requirements - Paragraph
3 - Point #2 - Rationale: models represent the 'why' of a change. Techniques
used to represent the rationale include Decision Modelling; Scope Modelling;
Business Model Canvas; Root Cause Analysis; and Business Rules Analysis
2. The main reason for implementing appropriate levels of abstraction is
because:
A. Not all stakeholders find value in the entire set of requirements
B. Requirements do not have necessary attributes
C. Requirements have missing components
D. Stakeholders don't have interest - correct answers✅✅A. Not all
stakeholders find value in the entire set of requirements
Explanation: BABoK V3.0 - Section 7.1.4.4 - Implement the Appropriate
Levels of Abstraction - The level of abstraction of a requirement varies based
on the type of requirement and audience for the requirement. Not all
stakeholders require or find value in the complete set of requirements and
models. It may be appropriate to produce different viewpoints of
requirements to represent the same need for different stakeholders. Business
analysts take special care to maintain the meaning and intent of the
requirements over all representations.
,ECBA Exam Questions and Answers A+
Guide
3. Which of the following is used to record the meaning of relevant business
terms while analyzing requirements?
A. Glossary
B. Scope model
C. State model
D. Data dictionary - correct answers✅✅A. Glossary
Explanation: BABoK V3.0 - Section 7.1.6 - Techniques - Glossary: used to
record the meaning of relevant business terms while analyzing requirements
4. Which of the following can be used for quality control when verifying
requirements and designs?
A. Data model
B. Templates
C. Information management approach
D. Checklists - correct answers✅✅D. Checklists
Explanation: BABoK V3.0 - Section 7.2.4.3 - Checklists - Checklists are used
for quality control when verifying requirements and designs.
5. Which of the following stakeholders can participate in specify and model
requirements task?
A. Only Sponsor and PM
, ECBA Exam Questions and Answers A+
Guide
B. Only developers and implementation SME
C. Only technical architect and PM
D. Any stakeholders - correct answers✅✅D. Any stakeholders
Explanation: BABoK V3.0 - Section 7.1.7 - Any stakeholder: business analysts
may choose to perform this task themselves and then separately package
and communicate the requirements to stakeholders for their review and
approval; or they might choose to invite some or all stakeholders to
participate in this task.
6. A set of conventions that define how requirements will be represented;
organized and related is known as:
A. Views
B. Viewpoints
C. Architecture
D. Attributes - correct answers✅✅B. Viewpoints
Explanation: BABoK V3.0 - Section 7.4.4.1 - Requirements Viewpoints and
Views A viewpoint is a set of conventions that define how requirements will
be represented; how these representations will be organized; and how they
will be related. Viewpoints provide templates for addressing the concerns of
particular stakeholder groups
7. If there are no relationships between requirements that link elements in
two different and conflicting ways; then the relationship satisfies which of the
following quality criteria?
A. Consistent