_____ _____ is the belief that there is a technique, method or process that is more
effective at delivering a particular outcome than any other - ANSWER> Best
Practice
A Best Practice is the belief that there is a ______ , _____ or _____ that is more
effective at delivering a particular outcome than any other. - ANSWER> -
technique
- method
- process
How many best practices are there? - ANSWER> 10
What are the 3 areas that the implementing techniques are categorized into? -
ANSWER> 1. Procurement
2. Contracting
3. Execution
All DB members should be _____ and _____ in the DB process and be
knowledgeable of the differences between DB and other delivery systems. -
ANSWER> - educated
- trained
, P a g e |2
The initial preliminary IDWP should have been included in the _____ stage --
refine and update. - ANSWER> Proposal
In IDWP, you should identify the level of _____ required for documentation of
each element. - ANSWER> detail
In IDWP, one should determine how much _____ will be allocated to each _____
task. - ANSWER> - time
- design
In IDWP, one should include _____ for periodic design reviews per contract. -
ANSWER> milestones
Integrated pull planning should be done for both _____ and ______. - ANSWER>
- design
- construction
What are 4 documents included in the Executive Agreements? - ANSWER> 1.
Owner's project criteria.
2. Design-Builder's proposal.
3. Enhancements list.
4. Agreement on price or GMP.
What are the 4 primary phases of oversight? - ANSWER> 1. Pre-con.
2. Contract Oversight.
3. Closeout.
, P a g e |3
4. Performance Evaluation
Formal partnering (or disputes review board) happens in which of the 4 primary
phases of oversight?
a) Pre-Con
b) Contract Oversight
c) Close-out
d) Performance Evaluation - ANSWER> a) Pre-Con
It is key to be accessible and flexible in which phase of oversight?
a) Pre-Con
b) Contract Oversight
c) Close-out
d) Performance Evaluation - ANSWER> b) Contract Oversight
In the Pre-Con phase of Oversight, one should confirm what constitutes _____
_____. - ANSWER> "Design Commitment"
The project team, at the outset of the project should establish processes to facilitate
timely and effective ______ , _____ and _____ ______. - ANSWER> -
communication
- collaboration
- issue resolution