The Test and Evaluation Master Plan (TEMP) must be developed prior to
which of the following? - -Milestone A and updated before each subsequent
review
-After a program successfully passes IOTE and begins full deployment, no
further test and evaluation activities take place. - -False
-Select the type of Operational Test and Evaluation that assesses crew
vulnerability required by Title 10 U.S.C 2366. - -ANSWER IS NOT
"Interoperability"
-Select the type of Operational Test and Evaluation assessment that is
conducted on prototype systems: - -Initial Operational Test and Evaluation
-Test and Evaluation (T&E) is important to decision makers because it - -
ANSWER IS NOT "Provides vital information regarding risk and risk
mitigation"
-Which type of test is conducted under realistic conditions? - -Operational
Test and Evaluation
-Test and Evaluation (T&E) is used to identify technical risk, verify
performance, and validate system utility throughout the defense system
acquisition life cycle - -True
-Select the type of Operational Test and Evaluation that is conducted after
the Full-Rate Production Decision: - -ANSWERS ARE NOT: "Follow-On
Operational Test and Evaluation" OR "Initial Operational Test and Evaluation"
-Which of the following best describes Test and Evaluation (T&E) - -Provide
the Office of Secretary of Defense with crucial information to use in budget
justification
-Which of the following Test and Evaluation (T&E) activity takes place at
Milestone A? - -ANSWER IS NOT "The Milestone Decision Authority (MDA)
considers any early operational assessments or test and evaluation results"
-For ACAT I Programs, a Test and Evaluation Master Plan (TEMP) is optional
and can be used at the discretion of the Milestone Decision Authority on
these programs. - -False
A’s (DAU ACQ 1010 - Module 8)
The Test and Evaluation Master Plan (TEMP) must be developed prior to
which of the following? - -Milestone A and updated before each subsequent
review
-After a program successfully passes IOTE and begins full deployment, no
further test and evaluation activities take place. - -False
-Select the type of Operational Test and Evaluation that assesses crew
vulnerability required by Title 10 U.S.C 2366. - -ANSWER IS NOT
"Interoperability"
-Select the type of Operational Test and Evaluation assessment that is
conducted on prototype systems: - -Initial Operational Test and Evaluation
-Test and Evaluation (T&E) is important to decision makers because it - -
ANSWER IS NOT "Provides vital information regarding risk and risk
mitigation"
-Which type of test is conducted under realistic conditions? - -Operational
Test and Evaluation
-Test and Evaluation (T&E) is used to identify technical risk, verify
performance, and validate system utility throughout the defense system
acquisition life cycle - -True
-Select the type of Operational Test and Evaluation that is conducted after
the Full-Rate Production Decision: - -ANSWERS ARE NOT: "Follow-On
Operational Test and Evaluation" OR "Initial Operational Test and Evaluation"
-Which of the following best describes Test and Evaluation (T&E) - -Provide
the Office of Secretary of Defense with crucial information to use in budget
justification
-Which of the following Test and Evaluation (T&E) activity takes place at
Milestone A? - -ANSWER IS NOT "The Milestone Decision Authority (MDA)
considers any early operational assessments or test and evaluation results"
-For ACAT I Programs, a Test and Evaluation Master Plan (TEMP) is optional
and can be used at the discretion of the Milestone Decision Authority on
these programs. - -False