Use the information below to construct a project network using the activity-on-node (AON) method in order to answer
questions that follow.
Activity ID Predecessor Duration (in days)
A None 3
B A 1
C A 4
D B 1
E B, C 2
F E 8
G D 2
H E 3
I F, G, H 1
J I 1
Question 1
Not yet answered
Marked out of 1.00
What is the earliest start (ES) time for activity I?
a. 7
b. 17
c. 12
d. 15
e. 9
Clear my choice
https://mymodules.dtls.unisa.ac.za/mod/quiz/attempt.php?attempt=21111720&cmid=941681 1/5
, 8/19/24, 11:11 AM Assessment 3
Question 2
Not yet answered
Marked out of 1.00
If Activity F is delayed by 2 days. What will happen to the rest of the project?
a. The whole project will be delayed by 2 days
b. There will be no impact on the project
Clear my choice
Question 3
Not yet answered
Marked out of 1.00
What is the late finish (LF) time for activity E?
a. 9
b. 13
c. 15
d. 14
e. 7
Clear my choice
Question 4
Not yet answered
Marked out of 1.00
Determine the duration it will take to complete this project using the AON method.
a. 19 days
b. 20 days
c. 14 days
d. 9 days
e. 11 days
Clear my choice
https://mymodules.dtls.unisa.ac.za/mod/quiz/attempt.php?attempt=21111720&cmid=941681 2/5