PUB3712 ASSIGNMENT 01 SEMESTER 2 2024
Question 1
Not yet answered
Marked out of 1.00
Flag question
Question text
Select the incorrect alternative. In order to develop a successful procurement strategy, an
institution or project manager needs to adhere to five basic principles:
a.
Emphasise the effectiveness of human resources management.
b.
Relate the specific procurement objectives to the general strategy of the institution or
programme.
c.
Cultivate close ties with key suppliers. Suppliers play a key role and sound relations with
them should be actively managed.
d.
Strategic risk issues and implications is likely to see more institutions adopting an
integrated approach to risk management.
Question 2
Not yet answered
Marked out of 1.00
Flag question
Question text
Select the correct alternative to fill the blank space in the sentence. “An important aspect of
programme quality planning is ______________.
a.
Benchmarking.
b.
Implementing.
c.
Development.
d.
Staffing.
Question 3
Not yet answered
Marked out of 1.00
Flag question
Question text
, According to Merlyn and Parkinson (1994) defined TQM as “the _______________
management methods, concepts, and beliefs into the culture of the organization to bring
about continuous improvement”. Select the correct alternative to complete the sentence.
a.
Integration of quality.
b.
Management of resources.
c.
Staff management.
d.
None of these options.
Question 4
Not yet answered
Marked out of 1.00
Flag question
Question text
Fill in the missing word. Programme risk management includes the processes of risk
identification, risk assessment, risk response development, and _____________________.
a.
Risk Identification.
b.
Risk hazards.
c.
Risk response control.
d.
All these options.
Question 5
Not yet answered
Marked out of 1.00
Flag question
Question text
State whether the statement is True or False. An organization chart is any graphic display of
the project detailing the lines of authority.
a.
True.
b.
False.
c.
None of these options.
Question 6
Not yet answered
Marked out of 1.00
Question 1
Not yet answered
Marked out of 1.00
Flag question
Question text
Select the incorrect alternative. In order to develop a successful procurement strategy, an
institution or project manager needs to adhere to five basic principles:
a.
Emphasise the effectiveness of human resources management.
b.
Relate the specific procurement objectives to the general strategy of the institution or
programme.
c.
Cultivate close ties with key suppliers. Suppliers play a key role and sound relations with
them should be actively managed.
d.
Strategic risk issues and implications is likely to see more institutions adopting an
integrated approach to risk management.
Question 2
Not yet answered
Marked out of 1.00
Flag question
Question text
Select the correct alternative to fill the blank space in the sentence. “An important aspect of
programme quality planning is ______________.
a.
Benchmarking.
b.
Implementing.
c.
Development.
d.
Staffing.
Question 3
Not yet answered
Marked out of 1.00
Flag question
Question text
, According to Merlyn and Parkinson (1994) defined TQM as “the _______________
management methods, concepts, and beliefs into the culture of the organization to bring
about continuous improvement”. Select the correct alternative to complete the sentence.
a.
Integration of quality.
b.
Management of resources.
c.
Staff management.
d.
None of these options.
Question 4
Not yet answered
Marked out of 1.00
Flag question
Question text
Fill in the missing word. Programme risk management includes the processes of risk
identification, risk assessment, risk response development, and _____________________.
a.
Risk Identification.
b.
Risk hazards.
c.
Risk response control.
d.
All these options.
Question 5
Not yet answered
Marked out of 1.00
Flag question
Question text
State whether the statement is True or False. An organization chart is any graphic display of
the project detailing the lines of authority.
a.
True.
b.
False.
c.
None of these options.
Question 6
Not yet answered
Marked out of 1.00